Table 2.3     Summary Table for Major Site Activities in the Reporting Month

Contract No.

Site Activities (March 2021)

ND/2019/01

(a)          Site clearance in Portion 1f;

(b)         Site clearance and soil nailing in Portion 2

(c)          Site clearance in Portion 3

(d)         Erection of temporary noise barrier, laying of rising mains and excavation in Portion 4

(e)          Site clearance, temporary soil nailing, stockpile of soil, construction of KW01 retaining wall, sheetpiling and excavation, and pipes laying in Portion 5

(f)          Site clearance, temporary soil nailing, sheetpiling and excavation, pipes laying, pre-bored H-piling, construction of KW01 retaining wall, construction site haul road in Portion 6a

(g)         Arsenic soil treatment works in Portion 6b

(h)         Site clearance, construction of temporary road for alternative Po Lau Road, construction of site accommodation in Area T2 and T3 , sheetpiling and excavation, pipes laying in Portion 7

(i)           Construction of retaining wall, slope cutting, soil nailing, slope drainage and maintenance access construction, excavation for Fresh Water Service Reservoir, RC construction of Flushing Water Service Reservoir in Portion 8a

(j)           Site clearance, ground investigation and trial pits in Portion 9b

(k)         Stockpile of soil, temporary slope protection works in Portion 9c

(l)           Sheetpiling and excavation, pipes laying in Portion 10a

(m)       Site Clearance in Portion 10b

(n)         Construction of chain-link fence in Portion 11a

(o)         Site clearance, laying off rising mains in Portion 11b

(p)         Sheetpiling and excavation, construction of chain-link fence in Portion 14

(q)         MIC modules delivery in Portion 16

ND/2019/02

(a)          Pre-bored Socketed H-pile

(b)         Hoarding erection

ND/2019/03

(a)          Road and Drainage work in Portion 1;

(b)         Portion 2 to Portion 20

-          Erection of Permanent Boundary Structure

-          Construction of Irrigation Channel

-          Geotechnical Works in Long Valley (Trail Pits)

-          Construction of Temporary Road in Long Valley

-          Asbestos Removal in Long Valley

-          Demolition of Existing Construction in Handed over Area

-          Construction of Storage Shed and Type 2 Storage House

-          Construction of Bird Hide

-          Construction of Outdoor Classroom

-          Wetland Creation & Restoration works after Obtaining Approval from AFCD

ND/2019/04

(a)           Site clearance

(b)           Tree felling

(c)           Predrilling

(d)           Socket H-piling

(e)           Bored piling

ND/2019/05

(a)           Bridge Foundation Works

-          Ground investigation works at FLN-2-B-DH015(P), D38, FLN3-DH016, ABH03, ABH04, D39(P), ABH10

-          Pre-drilling for bored piles at C2-02, C2-03, C3-02, C3-03, D1-04, D1-01 & E1-02, C1-04, C2-01, C2-04, C3-01, C3-02, D2-01, E2-01 & E1-02 & D2-03

-          Bored piling at D2-02, E3-02, E3-03, C4-03, C4-04, D2-01, E2-03, D1-03, E1-03, E2-01

-          Pile cap construction at HKYFB Cap P-02 and Cap AB.

-          Footing and pier construction at C4-01a and C4-01b.

(b)          Jockey Club Road

-          SB permanent footpath construction

-          Rockfill Slope

-          Gas main diversion by Towngas

-          Tree felling

(c)           Tai Wo Service Road West

-          Site formation works at Portion XIII

-          Site formation works at Portion XVIII

-          Phase 1 permanent road works

-          Phase 2 UU trial pits and diversion works

-          Phase 2 permanent road works

-          Stage 2 crossroad duct construction works

-          Site clearance and vehicular access at Portion XV & XX

-          Retaining wall FW06 & FW11 construction

-          Remaining structure removal after asbestos removal works at Portion XV

(d)          Tai Wo Service Road East

-          Backfilling of box culvert BC5

-          Drainage works

-          Water main works

-          Site Formation at Portion XII

(e)           Fanling Highway

-          Erection of temporary signboard for dismantle works of existing sign gantry E-DST11

-          Power supply switch over for existing sign gantry E-DST11

-          Road works for temporary road diversion for D2-03 construction

ND/2019/06

(a)          Finishing works and E&M installations for the Management Office Building (MOB) at Portion 4.

(b)         Off-site fabrication of steel column and steel truss of steel canopy in China.

(c)          Erection of the steel members of steel canopy at Portion 3.

(d)         Slope improvement works and hydroseeding works for Ma Wat River at Portion 6.

(e)          Construction of mini-piles for the ramp structure at Portion 3 and 5

(f)          Proof drilling for mini-piles for the ramp structure at Portion 3 and 5.

(g)         Construction of ground slab of the market stall area at Portion 3.

(h)         Construction of underground utilities in the final stage market at Portion 3.

ND/2019/07

(a)            Site clearance at Portion 1 and 2.

(b)           Erection of site hoarding at Portion 1.

(c)            G.I. works at Portion 1.

(d)           Construction of box culvert at Portion 2.

(e)            Filing works at Portion 2.

(f)            C&D waste disposal at Portion 1 and 2.