Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site Activities
(May 2021) |
ND/2019/01 |
(a)
Site clearance, excavation in Portion 3 (b)
Hydroseeding in Portion 4 (c)
Site Clearance, stockpile of soil, construction of KW01 retaining
wall, sheetpiling and excavation, pipes laying Site
clearance in
Portion 5 (d)
Site Clearance,
sheetpiling and excavation, pipes laying,
construction of KW01 retaining wall in Portion 6a (e)
Arsenic
soil treatment works in Portion 6b (f)
Site Clearance, Construction of temporary road for alternative Po
Lau Road, Construction of site accommodation in Area T2 and T3, sheetpiling and excavation, pipes laying, footing of
Noise Barries in Portion 7 (g)
Construction of Retaining Wall, slope cutting, soil nailing,
slope drainage and maintenance access construction, Excavation for Fresh
Water Service Reservoir, RC construction of Flushing Water Service Reservoir in
Portion 8a (h)
Sheetpiling for jacking
pit in Portion 8b (i)
Sheetpiling and
excavation in Portion 9b (j)
Stockpile of soil, temp. slope protection works in Portion 9c (k)
Sheetpiling and
excavation, pipes laying in Portion 10a (l)
Sheetpiling and excavation in Portion 10b (m)
Laying of rising mains, construction of MBR in
Portion 11b (n)
Sheetpiling and excavation , Construction of temporary sewage pumping
station in
Portion 14 (o)
Construction of CLC in Portion 16 |
ND/2019/02 |
(a)
Pre-bored
Socketed H-pile (b)
Tree felling (c)
Hoarding
erection |
ND/2019/03 |
(a)
Road and Drainage work in Portion 1; (b)
Portion 2
to Portion 20 -
Erection
of Permanent Boundary Structure -
Construction of Irrigation Channel -
Geotechnical Works in Long Valley
(Trail Pits) -
Construction of Temporary Road in Long
Valley -
Asbestos Removal in Long Valley -
Demolition of Existing Construction in
Handed over Area -
Construction of Storage Shed and Type
2 Storage House -
Construction of Bird Hide -
Construction of Outdoor Classroom -
Wetland Creation & Restoration
works after Obtaining Approval from AFCD |
ND/2019/04 |
(a)
Site clearance (b)
Tree felling (c)
Predrilling (d)
Socket H-piling (e)
Bored piling |
ND/2019/05 |
(a)
Bridge Foundation Works -
Ground investigation works at FLN3-DH016, ABH03,
ABH04, D39(P), ABH10. -
Pre-drilling for bored piles at B1(Portion I
& II), B2(Potion II), C1-01 & C1-02(Portion II), C1-04a, C2-02,
C3-02, C4-03, E3-01. Bored piling at D2-02, E3-02, E3-03, C4-03, C4-04,
D2-01, E2-03, D1-03, E1-03, E2-01. -
Bored piling at C2-03, C2-04, C3-01, C3-03b,
C3-04b, C4-03, D1-03, D1-04, D2-01, D2-02, E1-03, E1-04, E2-03 and B1. -
Pile cap construction at HKYFB Cap P-02 and Cap
AB, at pier E2-02, C4-03, C4-04, D1-01, E1-01, E3-03. -
Footing and pier construction at C4-01a and
C4-01b. (b)
Viaduct Works -
Segment Mould
fabrication and installation. -
Segment production line and segment storage yard
establishment -
First batch of precast segment production -
Pile cap and pier column construction for C4-01,
C4-04 and E2-02 -
CTC storage yard establishment -
Bearing fabrication for bridge C4 and C3 (c)
Jockey Club Road -
Southbound Footpath & Roadworks Modification -
Rockfill Slope (3SW-C/F63) -
Cut Slope and soil nail construction works
(3SW-A/C149) -
Install temporary electricity meters -
TTA implementation in Jockey Club Road for Towngas UU diversion works -
Geotechnical Instrumentation (No. FW51/DH01) (d)
Tai Wo Service Road West -
Implementation of TTA at Phase 2 for drainage
trial pit -
Implementation of TTA at Phase 2 for UU
diversion, utilities works, trial pit works -
Implementation of TTA at Phase 3 for Retaining
wall construction works (FW04,FW06, C430, C360) -
New Gas Main pipe construction Works -
New CLP pipe and HKT manhole construction -
Utilities Works -
Permeant road works -
Drainage works -
HKY Footbridge Staircase Dismantle Works -
Retaining wall construction works (FW04, FW05,
FW06, FW52) -
Trial pit for retaining wall (FW52) -
Plate load test for retaining wall (FW52) (e)
Tai Wo Service Road East -
Drainage works at Portion XI and XII -
Temporary Street Light Diversion -
Water main works -
Site Formation at Portion XII -
Site Clearance and Site Formation at Portion XI -
Wheel Washing Facilities at Portion XII (f)
Fanling
Highway -
Dismantle works of existing sign gantry E-DST11 -
Road Works for TTA on Diversion of Fanling Highway for Pier D2-03 Construction |
ND/2019/06 |
(a)
Finishing works and E&M installations for the Management Office
Building (MOB) at Portion 4 (b)
Off-site fabrication of steel column, steel truss and bracing of
steel canopy in China (c)
Erection of the steel members of steel canopy at Portion 3 (d)
Construction of retaining wall FW21 at Portion 6 (e)
Construction of ground slab of the market stall area and concrete
carriageway at Portion 3 (f)
Construction of underground utilities in the final stage market
at Portion 3 (g)
Installation of sheet piles for ELS for footings of additional
carriageway steel cover at Portion 3 |
ND/2019/07 |
(a)
Site clearance at Portion 1 and 2 (b)
Construction of box culvert in Portion 2 (c)
Filling works in Portion 2 (d)
C&D waste disposal in Portion 1 and 2 (e)
Tree felling / Disposal of yard waste in Portion 1 and 2 (f)
Construction of site haul road in Portion 1 |