12.1    
The major site activities, potential
environmental impacts and recommended mitigation measures for the coming three months are shown in Table 12.1.
Table
12.1    Summary Table for Site
Activities, Potential Environmental Impacts and Recommended Mitigation Measures
in the Coming Months
| Contract No. | Major Site Activities | Location/
  Working Period | Potential
  Environmental Impact | Recommended
  Mitigation Measures | 
| ND/2019/01 | (a)     
  Site
  clearance / tree felling | Portion 13 | -
  Construction Dust impact - Noise
  Impact (Construction Phase) - Water Quality
  Impact (Construction Phase) - Waste Management (Construction Waste) | Air -             
  Watering on
  exposed earth and haul road. -             
  Cover the
  stockpiles or dusty materials. -             
  Deploy
  water bowsers to water the haul road. -             
  Deploy
  mist-cannon on site -             
  Provide shelter
  with top and 3-sides for cement production activities. -             
  Cover the
  Arsenic-containing soil. -             
  Store the
  bulk cement in enclosed silo tank for soil treatment. -             
  Close the
  mechanical cover of the vehicles used for transporting dusty materials. -             
  Establish
  vehicle wheel washing facilities at vehicle exit points. -             
  Speed
  control of site vehicles. Noise -             
  Regular
  inspect of construction plants in good condition. -             
  Provide
  temporary noise screens if necessary. -             
  Use of
  Quiet plants (QPME) and working methods if possible. -             
  Sequencing
  operation of construction plants where practicable. -             
  Shut down
  the machines and plant if not in use. -             
  Only
  well-maintained plant to be operated on-site -             
  Mobile
  plant to be sited as far away from NSRs as possible practicable. -             
  Conduct
  noise monitoring regularly. -             
  Erect
  silent-up noise barrier at portion 6b.  Water -             
  Set up
  wastewater treatment system (AquaSed) on site -             
  Erect soil
  bund / temporary drain to divert /collect surface runoff. -             
  Maintain
  the drainage and wastewater treatment facilities. Waste /
  Chemical Management -             
  Sort out
  demolition debris and excavated materials from demolition works to recover
  reusable / recyclable portions -             
  Provide
  recycling bins on site,
  encourage reuse and recycle as much as possible. -             
  Provide
  drip trays for
  chemical containers. -             
  Chemical spill kit available on site. -             
  Chemical waste cabinet available on site. -             
  Chemical wastes to be stored in appropriate containers and collected
  by a licensed chemical waste collector. -             
  Delivery of yard waste to tree shredding facility for upcycling. | 
| (b)     
  Stockpile of soil | NIL | |||
| (c)      
  Excavation
  / Backfilling | Portion 6a, 7, 8a, 9b, 11b | |||
| (d)     
  Slope works | Portion 3 | |||
| (e)      
  Construction of noise barrier | Portion
  1c | |||
| (f)       Site Formation | Portion 1c, 2, 3, 5, 13 | |||
| (g)     
  Removal of
  existing structure | Portion 13 | |||
| (h)     
  Construction
  of subway | Portion 2 | |||
| (i)       
  Operation
  of HAC treatment facility  | Portion
  6b | |||
| (j)       
  Drainage works / watermains works | Portion 1a,
  2, 3, 6a, 7, 8a, 8b, 9b, 11b | |||
| (k)     Road Construction | Portion 2,
  7 | |||
| (l)       
  Trenchless | Portion
  8b | |||
| (m)   
  Construction of reservoir/receiving pit | Portions
  8a | |||
| (n)     
  Ground Treatment | Portions
  8b | |||
| (o)      Erection of hoarding | NIL | |||
| (p)      Sheet
  piling / ELS & pipe pile / Shoring | Portion 1a,
  2, 9b | |||
| (q)      District Cooling System | Portion 6a, 9b | |||
| (r)       Sewage works | NIL | |||
| (s)       Pipe jacking | Portion 5 | |||
| ND/2019/02 | (a)       
  Pipe
  Jacking | Portions 1, 2, 4,
  5 | Air, Noise, Waste | -             
  Dusty works should be
  spray water. Idle stockpile or slop should be
  covered by Tarpaulin sheet properly. -             
  Wheel washing should
  be carried out at every exit. -             
  Plants should be well
  maintained to prevent dark smoke and oil leakage. Idle plant should be turned
  off. -             
  Drip tray should be
  provided for all chemical and stationary plants. -             
  No construction works
  shall be carried out in restricted hours (7:00 pm to 7:00 am) unless CNP is
  obtained. -             
  Erect noise screen
  along site boundary. -             
  Waste should be
  sorted and dispose according to the Waste Management Plan -             
  No direct discharge
  of wastewater into storm drains is allowed. Wastewater must be de-silted
  before discharged in accordance with the water discharge license. -             
  Dull green barrier and ecological measures should be implemented
  according to the Ecological protection plan. | 
| (b)       Backfilling | Portion 10 | Air, Noise, Waste | ||
| (c)       
  Concreting | Portions 4,
  7, 8, 10 | Air, Noise, Water, Waste, Ecology | ||
| (d)       Bedding & Pipe Laying | Portion 5 | Air, Noise, Water, Waste, Ecology | ||
| (e)       
  ELS | Portions 4,
  5, 8 | Air, Noise, Water, Waste, Ecology | ||
| (f)       
  Sheet Pile Removal | NIL | NIL | ||
| (g)       Cut and Fill of Slope | Portion 4,
  5 | Air, Noise, Water, Waste | ||
| (h)      
  Sheet pile installation | Portion 5, 6, 7 | Air, Noise, Water, Waste | ||
| ND/2019/03 | (a)       
  Excavation
  & ELS | Portion 1, 1A, 2, 3, 4,
  4A, 4B, 5, 5A | -    
  Waste -    
  Air
  pollution -    
  Noise
  pollution | -             
  Dusty works should be sprayed with water or stockpile should be
  covered by Tarpaulin properly. -             
  Plants should have maintenance to prevent dark smoke and oil leakage.
  Idle plant should be turned off. -             
  Drip tray should be provided for all chemical and stationary plants. -             
  No construction works shall be carried out in restricted hours (7:00
  pm to 7:00 am) unless CNP is granted. -             
  Waste should be sorted and disposed according to Waste Management Plan. -             
  No direct discharge of wastewater into storm water drains is allowed. Wastewater
  must be desilted before discharging according to water discharge license. | 
| (b)      
  Site
  Clearance | Sections 7, 8 and 9 | -    
  Waste -    
  Air
  pollution -    
  Noise
  pollution | ||
| (c)       
  Tree
  Felling | Sections 6, 7, 8 and 9 | -    
  Waste -    
  Air
  pollution -    
  Noise
  pollution  | ||
| ND/2019/04 | (a)       
  Rebar Fixing, formwork erection and scaffolding
  erection | Bridge F, A1, A2, A3, Portion J, K, H | -    
  Air, Noise, Waste | -             
  Dusty works should be sprayed with water or stockpile should be
  covered by tarpaulin properly. -             
  Plants should have maintenance to prevent dark smoke and oil leakage.
  Idle plant should be turned off. -             
  Drip tray should be provided for all chemical and stationary plants. -             
  No construction works shall be carried out in restricted hours (7:00
  pm to 7:00 am) unless CNP is granted. -             
  Waste should be sorted and disposed according to Waste Management
  Plan. -             
  No direct discharge of wastewater into storm water drains is allowed.
  Wastewater must be desilted before discharging according to water discharge
  license. | 
| (b)      
  Pile cap | Bridge A1, A3 and Portion J, K | -    
  Air, Noise,
  Water, Waste | ||
| (c)       
  Grouting | Bridge
  F, A1, A2, A3 and
  Portion J, K, H | -    
  Air, Noise,
  Water, Waste | ||
| (d)      
  Sheet piling removal | Bridge A1, Portion F | -    
  Air, Noise,
  Water, Waste | ||
| (e)       
  Excavation
  & ELS | Portion J, H, K, X, S, F03, Bridge A1, A2, A3, F01 | -    
  Air, Noise,
  Waste | ||
| (f)       
  Road works | Portion B, J, H, U and VY | -    
  Air, Noise,
  Waste | ||
| (g)      
  Pre-drilling | NIL | -    
  NIL | ||
| (h)      
  Sheet piling | Portion B | -    
  Air, Noise,
  Waste | ||
| (i)        
  UU diversion | Portion J and K | -    
  Air, Noise,
  Waste | ||
| ND/2019/05 | (a)       
  ELS & Pile Cap Construction | NB69 Bay
  2~8 NB110 Bay
  6~7 | -    
  Construction
  Dust Impact -    
  Noise
  Impact -    
  Water
  Quality Impact (Construction Phase) -    
  Waste Management  (Construction
  Waste) -    
  Landscape
  and Visual  -    
  Cultural
  Heritage | Regular watering on exposed worksites and haul road. -             
  Stockpiling area should be provided with covers and water spraying
  system. -             
  Only well maintained plant to be operated on
  site. -             
  plant known to emit noise strongly in one direction, where possible,
  be orientated so that the noise is directed away from nearby NSRs. -             
  mobile plant to be sited as far away from NSRs as possible
  practicable. -             
  All open stockpiles of construction materials of more than 50m3 to be
  cove red with tarpaulin. -             
  Manholes to be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris
  being washed into the drainage system. -             
  All vehicles and plant to be cleaned before leaving a construction
  site to ensure no earth, mud, debris and the like is deposited by them on
  roads. -             
  Segregate and store different types of waste in different containers,
  skip or stockpiles to enhance reuse or recycling of materials and their
  proper disposal. -             
  Sort out demolition debris and ex cavated
  materials from demolition works to recover reusable/recyclable portions. -             
  Provide training to workers on appropriate waste management
  procedures, including waste reduction, reuse and recycling. -             
  To adopt other good site practice, such as arrangements for collection
  and effective disposal to an appropriate facility, of all wastes generated at
  the site and regular cleaning and maintenance programme
  for drainage. -             
  Chemical wastes to be stored in appropriate containers and collected
  by a licensed chemical waste Contractor. Chemical wastes (e.g. spent
  lubricant oil) should be recycled at an appropriate facility as far as
  possible, while the chemical waste that ca nnot be
  recycled should be disposed of at either the Chemical Waste Treatment Centre,
  or another licensed facility, in accordance with the Waste Disposal (Chemical
  Waste) (General) Regulation. -             
  Conducting Construction Vibration Monitoring -             
  Tree Protection & Preservation Exiting trees to be retained within
  the Project Site should be carefully protected during construction. In particular OVTs will be preserved according to ETWB
  Technical Circular (Works) No. 29/2004. -             
  Tree Transplantation Trees unavoidably affected by the Project works
  should be transplanted where practical. Trees should be transplanted straight
  to their final receptor site and not held in a temporary nursery as far as
  possible. -             
  Erect 2m high dull green site boundary fence. | 
| (b)      
  Cap Construction | E3-04a, E3-04b, E4-01 and E4-02 | |||
| (c)       
  Cross head
  construction | B2-01,
  B2-02 and B2-03 | |||
| (d)      
  Pier / Pier head Construction | D2-01
  and E305M | |||
| (e)       
  Fabrication for segment | C2, C1, D1, D2, E1, E4 | |||
| (f)       
  Form Traveler | E3-01 construction 3rd to 6th pair E2-02 construction 14th pair & dismantling of FT1 D2-02 construction 6th to 8th pair D2-03 construction 2nd pair to 4th pair E2-01 erection of 5th set of form traveler. | |||
| (g)       Segment Erection by Launching Girder & Crane | Bridges C3, C2 | |||
| (h)      
  SOP construction (precast & in-situ cast in type) | D2-01 | |||
| (i)        
  Road construction | TWSRW, TWSRE | |||
| (j)        
  Road works | Jockey Club Rd, TWSRW | |||
| (k)       Base slab construction | NB109
  ¡V bay 11~12 | |||
| (l)        
  Tree Works | All works areas | |||
| (m)     Drainage works | On
  Kui Street | |||
| ND/2019/06 | N/A | N/A | N/A | N/A | 
| ND/2019/07 | (a)       
  Road works | Portion 1, 4, 5 | -    
  Construction
  Dust Impact -    
  Noise
  Impact -    
  Water
  Quality Impact (Construction Phase) -    
  Waste
  Management (Construction Waste) -    
  Landscape
  and Visual | -             
  Regular watering on exposed worksites and haul road. -             
  Stockpiling area should be provided with covers and water spraying
  system. -             
  Only well-maintained plant to be operated on-site. -             
  plant known to emit noise strongly in one direction, where possible,
  be orientated so that the noise is directed away from nearby NSRs. -             
  mobile plant to be sited as far away from NSRs as possible
  practicable. -             
  All open stockpiles of construction materials of more than 50m3 to be
  covered with tarpaulin. -             
  Manholes to be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris
  being washed into the drainage system. -             
  All vehicles and plant to be cleaned before leaving a construction
  site to ensure no earth, mud, debris and the like is deposited by them on
  roads. -             
  Segregate and store different types of waste in different containers,
  skip or stockpiles to enhance reuse or recycling of materials and their
  proper disposal. -             
  Sort out demolition debris and excavated materials from demolition
  works to recover reusable/recyclable portions. -             
  Provide training to workers on appropriate waste management
  procedures, including waste reduction, reuse and recycling. -             
  To adopt other good site practice, such as arrangements for collection
  and effective disposal to an appropriate facility, of all wastes generated at
  the site and regular cleaning and maintenance programme
  for drainage. -             
  Chemical wastes to be stored in appropriate containers and collected
  by a licensed chemical waste Contractor. Chemical wastes (e.g. spent
  lubricant oil) should be recycled at an appropriate facility as far as
  possible, while the chemical waste that cannot be recycled should be disposed
  of at either the Chemical Waste Treatment Centre, or another licensed
  facility, in accordance with the Waste Disposal (Chemical Waste) (General)
  Regulation. -             
  Tree Protection & Preservation ¡V Exiting trees to be retained
  within the Project Site should be carefully protected during construction. In particular OVTs will be preserved according to ETWB
  Technical Circular (Works) No. 29/2004. -             
  Tree Transplantation ¡V Trees unavoidably affected by the Project works
  should be transplanted where practical. Trees should be transplanted straight
  to their final receptor site and not held in a temporary nursery as far as
  possible. -             
  Erect 2m high dull green site boundary fence. -             
  Light Control ¡V Construction day and night
  time lighting should be controlled to minimize glare impact to adjacent VSRs
  during the Construction phase. | 
| (b)      
  C&D waste disposal | Portion 1, 2, 4 | |||
| (c)       
  Filling works | Portions 2, 4 | |||
| (d)      
  Construction of site haul road | Portions 4 | |||
| (e)       
  Drainage Works | Portion 1, 2, 3, 4 | |||
| (f)       
  Sewerage works | Portion 3, 4 | |||
| (g)      
  Construction of Noise Barrier | Portion 5 | |||
| (h)      
  Waterworks | Portion 1, 2, 4 | |||
|  |  | 
12.2    
The major
site activities in coming three months are shown in Table IV.
12.3    
The
tentative environmental monitoring schedule for the next month is shown in Appendix
D.
12.4    
A
tentative construction programme is provided in Appendix A.