Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
Contract No. |
Site Activities (April
2025) |
ND/2019/01 |
(a)
Drainage
works, watermain works,
sheet piling and slope works
in Portion 1a (b)
Site
formation, watermain works, ELS construction, sewage
works, backfill and road works in
Portion 1c (c)
Site
formation, construction of subway, drainage
works, road
works and slope work in
Portion 2 (d)
HAC soil treatment, watermain works,
drainage works and
sheet piles in Portion 3 (e)
Site
formation, watermain works, drainage works and DCS pipe
work in Portion 5 (f)
Backfilling,
drainage works, watermain works, slope works, road works
and district cooling system in Portion 6a (g)
Operation
of HAC soil
treatment facility in Portion 6b (h)
Excavation, watermain works, sewage works, road works and
drainage works
in Portion 7 (i)
Road works, RC construction of fresh water service reservoir,
drainage works, watermain works, backfilling,
planting and metal works in
Portion 8a (j)
Ground Treatment, Trenchless work, grouting,
watermain construction and
ELS construction in Portion 8b (k)
Sheet
piling, excavation, drainage works, watermain works and district cooling system in
Portion 9b (l)
No activity in Portion 11b
this month (m)
Stockpile of soil
in Portion 13 |
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and Fill of Slope (e)
Sheet Piling (f)
Pipe
Jacking (g)
Pipe laying and bedding (h)
Grouting |
ND/2019/03 |
All
construction activities with significant environmental impact have been
substantially completed in
April 2024 and all outstanding works with defect rectification have also been
completed on 28 March 2025. |
ND/2019/04 |
(a)
Pile
Cap (b)
Back Filling (c)
Excavation (d)
Grouting (e)
Road works (f)
Formwork and Scaffolding Erection (g)
Rebar Fixing and ELS (h)
Backfilling (i)
S960
Delivery |
ND/2019/05 |
(a)
South
Team -
BBI
Toilet ¡V Backfilling and ABWF is in progress. -
Lift LT01
¡V Lift installation is in progress. -
FW54 ¡V
Footing and stem wall completed on 7 April 2025. -
E4
Retaining Wall ¡V Stem wall is 50% completed. -
E4 Ramp Utrough Bay 17~21 ¡V Footing is 60% completed. Bay 17 wall
construction and Bay 20 excavation is in progress. -
FW56 Bay
22~25 ¡V Footing and wall are 25% completed. Excavation for Bay 23 is in
progress. -
Noise
barrier NB109 Bay 5~19 A.
Backfilling
to formation was completed. Backfilling subbase in progress. B.
Installation
of noise barrier columns and concrete profile barrier was in progress. C.
Bay 1~4
Re-excavation resumed to expose couplers for construction of remaining part
of stem walls. -
Noise
barrier NB70 A.
Bay 1 to
6 ¡V Backfilling to formation was completed. -
Noise
barrier NB69 A.
Bay 1, 2a
¡V ELS in progress. -
Noise
barrier NB110 A.
Bay 10 ¡V
Stem wall was completed. TTA421C was implemented on 3 April 2025. -
Noise
barrier NB 29 Through Bay 1-23 A.
Footing
is 70%
completed B.
Wall
(exclude parapet) is 60% completed. Parapet section will cast after
backfilling to formation. -
Noise barrier NB 30 A.
Pre-bored
Socket H pile construction (187/211 nos) completed. B.
RC for
bay 18 & 20 completed & bay 13 to bay 17 in progress -
Noise barrier NB 77 A.
ELS works
for NB77 footing in progress. -
Fabrication
of Sign Gantry ¡V out of 20 Columns are completed. 6 columns are under
fabrication. -
Fabrication
of Noise Barrier ¡V NB27~31 noise barrier columns are under fabrication. (b)
North
Team -
Reinstatement
works & footpath in progress in C4-02 (HD) -
C1-01B
for viaduct drainage completed, C2-02 & B2-02 in progress. -
D1-01,
E2-01, C1-02 & C2-01 watermain works & pillar box for viaduct in
progress. -
Backfilling
of B2-02, B2-03, C1-01b & D2-01 in progress. -
JCR:
Construction of new central median & ducting works for traffic signal
& road light were completed of 96%. -
JCR &
Tong Hang Village J/O improvement works (FS 25): slope works 96 % completed. -
JCR &
Tong Hang Village J/O (near bus-stop) : Ducting
works for traffic signal & road light was in progress (
96 % completed). -
JCR near
F63 ¡Vslope feature construction works in progress. (c)
Bridges
and Structures -
All of 116 type C segments
were casted in DongGuan casting yard and delivered
to site. Total 115 segment were erected. -
All of 791 type A segments
were casted in HuiZhou casting yard and delivered
to site. Total 791 segment were erected. -
LG launching to B1-02
completed, erection of end span segment from B1-02 to B2-01 in progress. -
Installation of parapet
and central median for bridge C1 -
Installation of deck void
drainage at Bridge B2 in progress. -
Reinstate of lifting tower
NF83A in progress. -
D1-04 end span segment
erection completed. -
Installation of movement
joint C2-04b and C4-04b completed. Total 4 nos out
of 20 MJ installation completed. -
Water proofing for Bridge
E1,C4R,C3R completed, water
proofing for bridge C2R in progress. -
Asphalt paving on the deck
in progress, started from Bridge C3R. -
Installation of railing
and noise barrier on bridge deck in progress. -
B1-01 diaphragm beam
construction in progress. (d)
Form Traveler -
Dismantling
of form traveler at E3-04 & D2-01 completed. -
Parapet
installation at D2 bridge in progress. |
ND/2019/06 |
The construction phase was
completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 3 and 4 (b)
C&D waste disposal at Portion 2 and 4 (c)
Filling works at Portion 2 (d)
Construction of site haul road at Portion 4 (e)
Drainage works at Portion 1, 2, 3 and 4 (f)
Sewerage works at Portion 3 and 4 (g)
Construction
of noise barrier at Portion 4 (h)
Waterworks at Portion 1, 2, 3 and 4 |