Table IV Summary Table for Site Activities in the coming Three
Months
Contract
No. |
Site
Activities (May to July 2025) |
ND/2019/01 |
(a)
Drainage
works, watermain works, sheet piling, site formation and slope works in Portion 1a (b)
Watermain works in Portion
1b (c)
Site
formation, drainage works, watermain works, construction of noise barrier, road lighting works, ELS construction, sewage
works, backfilling and road works in
Portion 1c (d)
Site
formation, construction of subway, road works, drainage works,
slope works and soil nail in
Portion 2 (e)
HAC soil treatment, site formation, excavation, road works, slope
work, drainage works, watermain works and
soil nail in Portion 3 (f)
Site formation, sewage
works, excavation, backfilling, road works and
construction of public lighting in
Portion 5 (g)
Drainage
works, backfilling, road works, watermains
works, construction of retaining wall, slope works,
district cooling system works and road lighting works in Portion 6a (h)
Operation
of HAC treatment facility in Portion 6b (i)
Sheet
piling, excavation, stockpile of soil, drainage works, watermain works and
road works in Portion 7 (j)
Road works, drainage works, watermain works,
soil nail, planting and metal works in
Portion 8a (k)
Ground
treatment, trenchless works, watermain works, grouting,
ELS construction and chamber construction in
Portion 8b (l)
Sheet
piling, ELS construction, road
works, drainage works, watermain
works, district cooling system works, grouting works
and public lighting in
Portion 9b (m)
Backfilling in Portion 9c (n)
Sewage works, drainage
works, road works, backfilling, excavation and sheet piling in Portion 10b (o)
Site formation,
excavation, drainage works, roadworks and watermain works in Portion 11b (p)
Stockpile
of soil in Portion 13 |
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and
Fill of Slope (e)
Sheet Piling (f)
Pipe Jacking (g)
Pipe
laying and bedding (h)
Grouting |
ND/2019/03 |
The construction phase has been completed since
28 March 2025. |
ND/2019/04 |
(a)
Pile Cap (b)
Back
Filling (c)
Excavation (d)
Grouting (e)
Road
works (f)
Formwork
and Scaffolding Erection (g)
Rebar
Fixing and ELS (h)
Backfilling |
ND/2019/05 |
(a)
Backfilling (b)
Drainage works (c)
Water works (d)
Ducting and Road works (e)
Slope works (f)
Segments erection (g)
ELS (h)
Wall construction |
ND/2019/06 |
The construction phase has been completed and
handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road
works at Portion 1, 3 and
4 (b)
C&D
waste disposal at Portion 2 and 4 (c)
Filling Works at Portion 2 (d)
Construction of site haul
road at Portion 4 (e)
Drainage
works at Portion 1, 2,
3 and 4 (f)
Sewerage
works at Portion 3 and 4 (g)
Construction
of noise barrier at Portion 4 (h)
Waterworks
at Portion 1, 2, 3
and 4 |