11
ENVIRONMENTAL NON-CONFORMANCE
11.1
Six (6) Limit Level for DO, three (3) Limit Level
for turbidity of impact water quality monitoring were recorded. After investigation, all the
exceedance at SYR-IS1, NTR-IS1, SHST-IS2 and MWR-IS3 were considered caused by
other external factors rather than the contract works.
11.2
No Action/Limit Level exceedance for air quality, construction noise, ambient
arsenic, built heritage and landfill gas monitoring was recorded in the
reporting month. The summary of exceedance record in the reporting month is
shown in Appendix O.
11.3
Ecological
monitoring was carried out in the reporting month. Two (2) limit level
exceedance for aquatic fauna were recorded. The
exceedance were considered non-project related.
11.4 The exceedances were considered
non-project related, as no evidence to suggest that the exceedances were
related to project activities, supported by environmental monitoring data.
11.5
Should
the monitoring results of the environmental monitoring parameters at any
designated monitoring stations indicate that Action / Limit Levels are
exceeded, the actions in accordance with the Event/Action Plan in Appendix N would be carried out.
Summary
of Environmental Non-Compliance
11.6
No
environmental non-compliance was recorded in the reporting month.
Summary of
Environmental Complaint
11.7
No environmental complaint was received in the
reporting month. The Cumulative Complaint
Log since the commencement of the Project is presented in Appendix S.
Summary
of Environmental Summon and Successful Prosecution
11.8
There was
no successful environmental prosecution or notification of summons received
since the Project commencement. The Cumulative Log for environmental summon and
successful prosecution since the commencement of the Project is presented in Appendix T.