Table 2.3     Summary Table for Major Site Activities in the Reporting Month

Contract No.

Site Activities (August 2025)

ND/2019/01

(a)          Drainage works, watermain works, sheet piling and slope works in Portion 1a

(b)         Site formation, watermain works, ELS construction, drainage works, sewage works, backfilling and road works in Portion 1c

(c)          Site formation, construction of subway, drainage works, road works, soil nail and slope works in Portion 2

(d)         HAC soil treatment and watermain works in Portion 3

(e)          UU works, site formation, watermain works and drainage works in Portion 5

(f)          Backfilling, drainage works, watermain works, slope works, road works, district cooling system and UU works in Portion 6a and 9c

(g)         Operation of HAC soil treatment facility in Portion 6b

(h)         Excavation, watermain works, sewage works, road works (UU) and drainage works in Portion 7

(i)           Road works, RC structure works, drainage works, watermains works, backfilling, planting, metal works, slope works and E&M works in Portion 8a

(j)           Ground treatment, grouting, watermain construction, ELS construction and RC structure works in Portion 8b

(k)         Sheet piling, excavation, road works, drainage works, watermain works and district cooling system in Portion 9b

(l)           Drainage works and watermain works in Portion 11b

(m)       Stockpile of soil in Portion 13

ND/2019/02

(a)           Backfilling

(b)           Excavation

(c)            Concreting

(d)           Cut and Fill of Slope

(e)            Sheet Piling

(f)            Pipe Jacking

(g)           Pipe laying and bedding

(h)           Grouting

ND/2019/03

All construction activities with significant environmental impact have been substantially completed in April 2024 and all outstanding works with defect rectification have also been completed on 28 March 2025.

ND/2019/04

(a)           Back Filling

(b)           Excavation

(c)           Grouting

(d)           Road works

(e)           Formwork and Scaffolding Erection

(f)            Rebar Fixing and ELS

(g)           Backfilling

(h)           Concreting

(i)            MIC

ND/2019/05

(a)          South Team

-          BBI Toilet ¡V ABWF and installation bio treatment plant were in progress.

-          BBI Toilet ¡V Dwarf Wall construction was 70% completed.

-          Lift LT01 ¡V Lift installation was completed. Testing in progress.

-          Road D400 ¡V TTA-469 implemented on 20 July 2025.

-          ADS21 PC1 ¡V Sheetpiling works in progress.

-          ADS21 PC2 ¡V Protective measures for water main and trial pits for CLP132kV in progress.

-          DS11 ¡V Sheetpiling for footing construction was in progress.

-          D2-02 ¡V Watermain laying for fire hydrant was in progress.

-          E2-03 ¡V Outfall construction was in progress.

-          E3-01 ¡V Removal of temporary working platform was still in progress.

-          E4 Retaining Wall ¡V Temporary ramp to Bridge E4 was completed on 8 August 2025.

-          E4 Ramp Utrough Bay 17~21 ¡V Stem walls were all completed up to bottom of profile barrier.

-          FW56 Bay 22~25 ¡V Stem walls were in progress.

-          Noise barrier NB109 and NB70

A.         Northbound ¡V Installation of concrete profile barrier at NB109 Bay 1~4 was in progress.

B.          Southbound ¡V TTA-452 was implemented on 9 July 2025. Construction of remaining NB70 foundation shall resume after implementation of TTA-488.

-          Noise barrier NB69 and NB68

A.         NB69 ¡V Bay 1~2a stem wall was completed.

B.          NB68 ¡V Bay 7 stem wall was in progress. ELS for Bay was completed and sheet piling for Bay 1~5 was in progress.

-          Noise barrier NB 108

A.         Additional trial pits required by WSD were completed.

B.          TCSS ducting and cables were found in conflict with the piling works. Cable slewing was in progress.

-          Remaining part of existing sign gantry FADS8 was removed on 6 August 2025. Noise Barrier NB29 Trough Bay 1-23

A.         Footing is 85% completed

B.          Wall (exclude parapet) is 80% completed. Parapet section will cast after backfilling to formation.

-          Noise barrier NB 30

A.         Bay 1 to bay 20 blinding completed.

B.          RC from bay 1 to bay 7, & bay 15 to bay 20 completed & bay 10,13 & 14 in progress.

-          Noise barrier NB 77

C.          NB77 pile cap completed, wall construction in progress.

-          Sign Gantry

A.         11 out of 20 Columns fabrication were completed. 10 Columns were installed.

B.          4 out of 11 Mid Chords fabrication were completed. DS21B mid chord was in progress.

C.          4 out of 11 sign gantries were installed on site.

D.         Installation of DS21A was completed on 8 August 2025.

-         Fabrication of Noise Barrier ¡V 36% of overall noise barrier columns were completed. Fabrication of NB30 noise barrier column was in progress.

(b)         North Team

-          C1-03 catch pit & manhole construction in progress. D2-01 & B2-03 completed.

-          D1-01, E2-01, C1-02 & C2-01 watermain works & pillar box for viaduct completed. D1-04 in progress.

-          Backfilling of B2-03, B2-01, C1-01b & D2-01 in progress.

-          JCR: Construction of new central median & ducting works for traffic signal & road light were completed of 100%.

-          JCR & Tong Hang Village J/O improvement works (FS 25): slope works 98 % completed.

-          JCR & Tong Hang Village J/O (near bus-stop) : Ducting works for traffic signal & road light was in progress (100 % completed).

-          JCR near F63 ¡Vslope feature construction works completed. Street furniture in progress.

-          JCR resurfacing in progress (40% completed)

(c)          Bridges and Structures

-          Dismantle of LG completed.

-          Installation of parapet and central median for bridge in progress.

-          Installation of fire hydrant in progress. Fire hydrant at pier C2-01,C3-03 completed.

-          Reinstate of lifting tower NF83A in progress.

-          Installation of movement joint E1-04 in progress. Total 8 of 20 MJ installation completed.

-          Water proofing on bridge deck in progress, bridge D1, E1, C4R, C3R, C2R, C4L, C3L, C2L completed.

-          Asphalt paving on the deck in progress, base course of bridge D1, E1, C4R, C3R, C2R, C4L, C3L, C2L completed.

-          Wearing course pavement on the deck in progress.

-          Installation of railing and noise barrier on bridge deck in progress.

-          E3 & D2 external tendon in progress.

ND/2019/06

The construction phase was completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)        Road works at Portion 3

(b)        C&D waste disposal at Portion 2 and 4

(c)        Waterworks at Portion 3