Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
Contract No. |
Site Activities (August
2025) |
ND/2019/01 |
(a)
Drainage
works, watermain works,
sheet piling and slope works
in Portion 1a (b)
Site
formation, watermain works, ELS construction, drainage works, sewage works,
backfilling and road works in Portion 1c (c)
Site
formation, construction of subway, drainage works, road works, soil nail and
slope works in
Portion 2 (d)
HAC soil treatment and watermain works in Portion 3 (e)
UU works,
site formation, watermain works and drainage works in Portion 5 (f)
Backfilling,
drainage works, watermain works, slope works, road works, district cooling
system and UU works in
Portion 6a and 9c (g)
Operation
of HAC soil
treatment facility in Portion 6b (h)
Excavation,
watermain works, sewage works, road works (UU) and drainage works in Portion
7 (i)
Road works, RC structure
works, drainage works, watermains works, backfilling, planting, metal works,
slope works and E&M works in
Portion 8a (j)
Ground treatment,
grouting, watermain construction, ELS construction and RC structure works in Portion 8b (k)
Sheet
piling, excavation, road works, drainage works, watermain works and district
cooling system in Portion 9b (l)
Drainage works and
watermain works in Portion 11b (m)
Stockpile of soil
in Portion 13 |
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and Fill of Slope (e)
Sheet Piling (f)
Pipe
Jacking (g)
Pipe laying and bedding (h)
Grouting |
ND/2019/03 |
All
construction activities with significant environmental impact have been
substantially completed in
April 2024 and all outstanding works with defect rectification have also been
completed on 28 March 2025. |
ND/2019/04 |
(a)
Back Filling (b)
Excavation (c)
Grouting (d)
Road works (e)
Formwork and Scaffolding Erection (f)
Rebar Fixing and ELS (g)
Backfilling (h)
Concreting (i)
MIC |
ND/2019/05 |
(a)
South
Team -
BBI
Toilet ¡V ABWF and installation bio treatment plant were in progress. -
BBI
Toilet ¡V Dwarf Wall construction was 70% completed. -
Lift LT01
¡V Lift installation was completed. Testing in progress. -
Road D400
¡V TTA-469 implemented on 20 July 2025. -
ADS21 PC1
¡V Sheetpiling works in progress. -
ADS21 PC2
¡V Protective measures for water main and trial pits for CLP132kV in progress. -
DS11 ¡V
Sheetpiling for footing construction was in progress. -
D2-02 ¡V
Watermain laying for fire hydrant was in progress. -
E2-03 ¡V
Outfall construction was in progress. -
E3-01 ¡V
Removal of temporary working platform was still in progress. -
E4
Retaining Wall ¡V Temporary ramp to Bridge E4 was completed on 8 August 2025. -
E4 Ramp
Utrough Bay 17~21 ¡V Stem walls were all completed up to bottom of profile
barrier. -
FW56 Bay
22~25 ¡V Stem walls were in progress. -
Noise
barrier NB109 and NB70 A.
Northbound
¡V Installation of concrete profile barrier at NB109 Bay 1~4 was in progress. B.
Southbound
¡V TTA-452 was implemented on 9 July 2025. Construction of remaining NB70
foundation shall resume after implementation of TTA-488. -
Noise
barrier NB69 and NB68 A.
NB69 ¡V
Bay 1~2a stem wall was completed. B.
NB68 ¡V
Bay 7 stem wall was in progress. ELS for Bay was completed and sheet piling
for Bay 1~5 was in progress. -
Noise
barrier NB 108 A.
Additional
trial pits required by WSD were completed. B.
TCSS
ducting and cables were found in conflict with the piling works. Cable
slewing was in progress. -
Remaining part of existing
sign gantry FADS8 was removed on 6 August 2025. Noise Barrier NB29 Trough Bay
1-23 A.
Footing
is 85% completed B.
Wall
(exclude parapet) is 80% completed. Parapet section will cast after
backfilling to formation. -
Noise barrier NB 30 A.
Bay 1 to
bay 20 blinding completed. B.
RC from
bay 1 to bay 7, & bay 15 to bay 20 completed & bay 10,13 & 14 in
progress. -
Noise barrier NB 77 C.
NB77 pile
cap completed, wall construction in progress. -
Sign Gantry A.
11 out of
20 Columns fabrication were completed. 10 Columns were installed. B.
4 out of
11 Mid Chords fabrication were completed. DS21B mid chord was in progress. C.
4 out of
11 sign gantries were installed on site. D.
Installation
of DS21A was completed on 8 August 2025. -
Fabrication
of Noise Barrier ¡V 36% of
overall noise barrier columns were completed. Fabrication of NB30 noise
barrier column was in progress. (b)
North
Team -
C1-03
catch pit & manhole construction in progress. D2-01 & B2-03
completed. -
D1-01,
E2-01, C1-02 & C2-01 watermain works & pillar box for viaduct
completed. D1-04 in progress. -
Backfilling
of B2-03, B2-01, C1-01b & D2-01 in progress. -
JCR:
Construction of new central median & ducting works for traffic signal
& road light were completed of 100%. -
JCR &
Tong Hang Village J/O improvement works (FS 25): slope works 98 % completed. -
JCR &
Tong Hang Village J/O (near bus-stop) : Ducting works for traffic signal
& road light was in progress (100 % completed). -
JCR near
F63 ¡Vslope feature construction works completed. Street furniture in
progress. -
JCR
resurfacing in progress (40% completed) (c)
Bridges
and Structures -
Dismantle of LG completed. -
Installation of parapet
and central median for bridge in progress. -
Installation of fire
hydrant in progress. Fire hydrant at pier C2-01,C3-03 completed. -
Reinstate of lifting tower
NF83A in progress. -
Installation of movement
joint E1-04 in progress. Total 8 of 20 MJ installation completed. -
Water
proofing on bridge deck in progress, bridge D1, E1, C4R, C3R, C2R, C4L, C3L,
C2L completed. -
Asphalt
paving on the deck in progress, base course of bridge D1, E1, C4R, C3R, C2R,
C4L, C3L, C2L completed. -
Wearing
course pavement on the deck in progress. -
Installation
of railing and noise barrier on bridge deck in progress. -
E3 &
D2 external tendon in progress. |
ND/2019/06 |
The construction phase was
completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 3 (b)
C&D waste disposal at Portion 2 and 4 (c)
Waterworks at Portion 3 |