Table IV       Summary Table for Site Activities in the coming Three Months

Contract No.

Site Activities (September to November 2025)

ND/2019/01

(a)          Drainage works, watermain works, sheet piling, site formation, slope works and road works in Portion 1a

(b)         Site formation, watermain works, ELS construction, drainage works, sewage works, backfilling, UU works and road works in Portion 1b and 1c

(c)          Site formation, construction of subway, road works, drainage works, slope works and soil nail in Portion 2

(d)         HAC soil treatment and watermain works in Portion 3

(e)          Watermain works, drainage works, smart lighting and paving block in Portion 5

(f)          Backfilling, drainage works, watermain works, slope works, road works and UU works in Portion 6a and 9c

(g)         Operation of HAC treatment facility in Portion 6b

(h)         Excavation, drainage works, watermains works, sewage works, road works and smart lighting in Portion 7

(i)           Road works, RC structure works, drainage works, watermains works, backfilling, planting, metal works, slope works and E&M works in Portion 8a

(j)           Ground treatment, grouting, watermain works, ELS construction and RC structure works in Portion 8b

(k)         Excavation, road works, drainage works, watermain works and district cooling system works in Portion 9b

(l)           Excavation, watermain works, drainage works, road works and smart lighting. in Portion 11b

(m)       Stockpile of soil in Portion 13

ND/2019/02

(a)            Backfilling

(b)           Excavation

(c)            Concreting

(d)           Cut and Fill of Slope

(e)            Sheet Piling

(f)            Pipe Jacking

(g)           Pipe laying and bedding

(h)           Grouting

ND/2019/03

The construction phase has been completed since 28 March 2025.

ND/2019/04

(a)           Back Filling

(b)           Excavation

(c)           Grouting

(d)           Road works

(e)           Formwork and Scaffolding Erection

(f)            Rebar Fixing and ELS

(g)           Backfilling

(h)           MIC

ND/2019/05

(a)        Backfilling

(b)       Drainage works

(c)        Water works

(d)       Ducting and Road works

(e)        Slope works

(f)        Segments erection

(g)       ELS

(h)       Wall construction

ND/2019/06

The construction phase has been completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)        Road works at Portion 3

(b)        C&D waste disposal at Portion 2 and 4

(c)        Waterworks at Portion 3