2.1
The Kwu Tung North
(KTN) and Fanling North (FLN) New Development Areas
(NDAs) are one of the important sources of land and housing supply in the
medium and long term. The development of the KTN and FLN NDAs will be
implemented in phase for full completion by 2031. The Phase 1 of the NDAs development,
comprising the Advance Works and First Stage Works, is targeted to be
implemented from the second half of 2019 progressively. The Advance and First
Stage Works would include site formation, engineering infrastructure works
(including roads, drainage, sewerage, waterworks, landscaping works, pumping
stations, and fresh water and flushing water service reservoirs), soil
remediation, reprovisioning of North District Temporary Wholesale Market,
development of a nature park at Long Valley and implementation of environmental
mitigation measures.
2.2
The scope of works under the Advance and First
Stage Works comprises the following:
a)
The Advance Works (PWP item No. 7747CL-2)
consist of:
i)
site formation of land (including soil
remediation) in KTN and FLN NDAs for housing, community facilities and
engineering infrastructure;
ii)
construction of roads including the eastern
section of Fanling Bypass (FLBP(E)) connecting the
FLN NDA to Fanling Highway and other roads with
footpaths and cycle tracks, and associated junction/ road improvements;
iii)
engineering infrastructure works including
drainage. Sewerage (including two sewage pumping stations), waterworks
(including a fresh water service reservoir and a flushing water service
reservoir in the KTN NDA), landscape works and slopeworks;
iv)
part expansion and upgrading of Shek Wu Hui
Sewage Treatment Works (SWHSTW);
v)
reprovisioning works; and
vi)
implementation of environmental mitigation
measures and environmental monitoring and audit (EM&A) programme
for the works mentioned in (i) to (v) above.
b)
The First Stage Works (PWP item No. 7759CL)
consist of:
i)
development of a nature park at Long Valley
including provision of a visitor centre and a
footbridge spanning across Sheung Yue River for connection between these two
facilities;
ii)
reprovisioning of two egretry
sites in the FLN NDA and enhancement works to an existing egretry
site in the KTN NDA;
iii)
site formation of land for a village resite area and a district police station in the KTN NDA;
iv)
engineering infrastructure works including
roads, drainage, sewerage, waterbirds, and landscape works; and
v)
implementation of environmental mitigation
measures and environmental monitoring and audit (EM&A) programme
for the works mentioned in (i) to (iv) above.
2.3
The Project which covers KTN and FLN NDAs is a
designated project (DP) under Schedule 3 of the Environmental Impact Assessment
(EIA) Ordinance (Cap. 499). In October 2013, the EIA Report (AEIAR-175/2013)
for the Project was approved by the Director of Environmental Protection
pursuant to the EIA Ordinance. The relevant EPs under the Project and the
respective Work Contracts are summarised in Tables 2.1a and 2.1.b.
Table 2.1a Summary
of EPs under the Project and the Respective Work Contracts
EP
No. |
Designated
Project |
C1 |
C2 |
C3 |
C5A |
C5B |
C6 |
C7 |
|
Castle Peak Road Diversion |
ü |
¡@ |
|||||||
Kwu
Tung North New Development Area Road P1 and P2 and Associated New Kwu Tung Interchange and Pak Shek Au Interchange
Improvement |
ü |
¡@ |
|||||||
Kwu
Tung North New Development Area Road D1 to D5 |
ü |
ü |
¡@ |
||||||
Sewage Pumping Stations in Kwu
Tung North New Development Area |
ü |
¡@ |
|||||||
Utilization of Treated Sewage Effluent (TSE) from
Shek Wu Hui Sewage Treatment Works |
ü |
¡@ |
|||||||
Fanling
Bypass Eastern Section |
ü |
ü |
ü |
¡@ |
|||||
Reprovision of temporary Wholesale Market in Fanling North New Development Area |
ü |
¡@ |
|||||||
EP-546/2017 |
Fanling
North Temporary Sewage Pumping Station |
ü |
¡@ |
Notes:
C1: ND/2019/01 C2:
ND/2019/02 C3: ND/2019/03 C5A: ND/2019/04
C5B: ND/2019/05 C6:
ND/2019/06 C7: ND/2019/07
Table 2.1b Summary of Scope of Works under concerned EP
Environmental Permit (EP)
No. |
Work Contract(s) |
Scope of Works under
concerned EP(s) |
Site Layout Plan under
concerned EP(s) |
EP-466/2013/A(Part) |
C1 |
Realign Castle Peak Road and join with the
Pak Shek Au Interchange at the western end |
Figure 12 |
EP-467/2013/A(Part) |
C1 |
Construction of new primary distributor road
(P1) within Kwu Tung North New Development Area |
Figure 13 |
EP-468/2013/A(Part) |
C1 |
Construction of new primary distributor
roads (D1, D3, D4 and part of D5) within Kwu Tung
North New Development Area |
Figure 14 |
C3 |
Development of a nature park at Long Valley
and ecological mitigation and enhancement works for the nature park
(Condition 2.9) |
Figure 15 |
|
EP-469/2013(Part) |
C2 |
Construction of one sewage pumping station
in Kwu Tung North with installed capacity of more
than 2,000 m3 per day |
Figure 16 |
EP-470/2013/A(Part) |
C1 |
Construction of service reservoir and
watermain for the reuse of treated sewage effluent for reuse in Kwu Tung North Development Areas |
Figure 17 |
EP-473/2013/A(Part) |
C3 |
Establishment
of alternative egretry sites and enhance the existing egretry
site at Ho Sheung Heung and/or its vicinity (Condition 2.7) |
Figure 18 |
EP-473/2013/A(Part) |
C5A |
Construction of new district distributor
inside FLN NDA, which provides a linkage between the Man Kam To Road and the
proposed Fanling Bypass Eastern Section |
Figure 19 |
EP-473/2013/A(Part) |
C5B |
Figure 20 |
|
EP-475/2013/A |
C6 |
The re-provisioned wholesale market will
have approximately 1,000 market stalls within a site area of around 1.3 ha |
Figure21 |
EP-546/2017 |
C5A |
Construct and operate a temporary sewage
pumping station in Fanling North with installed
capacity (average dry weather flow) of about 3,600m3/day |
Figure 22 |
Remark:
The EP(s) not related to the Project of the First Phase of the Kwu
Tung North (KTN) and Fanling North (FLN) New
Development Area (NDA) Development Areas are not included in the Table.
2.4
The site boundary of the Project and all Works
Contracts are shown in Drawing No. 1.
2.5
The required submissions and submission status
under Environmental Permits are shown in Appendix
U.
2.6
The site layout plans under concerned Environmental Permits are shown in Figures 12 - 22.
2.7
Different parties with different levels of
involvement in the Project organisation include:
Project Proponent ¡V Civil Engineering and
Development Department (CEDD)
Supervisor / Supervisor's Representative ¡V AECOM Asia Co. Ltd.
Environmental Team (ET) ¡V Wellab
Limited
Independent Environmental Checker (IEC) ¡V Mott MacDonald Hong Kong Ltd (MottMac)
2.8
The names and contact numbers of key personnel are summarised
in Table 2.2.
Table 2.2 Key Contacts of the Project
Party |
Role |
Contact Person |
Phone No. |
Fax No. |
Civil Engineering and Development Department,
HKSAR (CEDD) |
Project Proponent |
Mr. Ryan Chau |
3797 5387 |
3547 1658 |
Supervisor / Supervisor's Representative (AECOM Asia Co. Ltd.) |
Chief Resident Engineer |
Mr. Alan Lee |
6398 5982 |
2680 9515 |
Senior Resident Engineer |
Mr. King-man Chan |
9651 2635 |
2680 9515 |
|
Environmental Team (Wellab
Limited) |
Environmental
Team Leader |
Dr. Priscilla Choy |
2898 7388 |
2898
7076 |
Independent Environmental Checker (MottMac) |
Independent Environmental Checker |
Mr. Thomas Chan |
2828 5967 |
2827 1823 |
Contract No. ND/2019/01 Contractor (Build King ¡V Richwell
Engineering Joint Venture) |
Site Agent |
Mr. Ivan Leung |
9640 8340 |
-- |
Environmental Officer |
Mr. Edward Tam |
9287 8270 |
||
Contract No. ND/2019/02 Contractor (Chun Wo ¡V Kwan Lee Joint Venture.) |
Site Agent |
Mr. Andy Chan |
3485 9780 |
-- |
Environmental Officer |
Ms. Barbara Yiu |
9758 2034 |
||
Contract No. ND/2019/03 Contractor (Sang Hing Kuly
Joint Venture) |
Site Agent |
Mr. Tang Wing Kai |
9300 7037 |
-- |
Environmental Officer |
Mr. Ken Cheung |
9803 5297 |
||
Contract No. ND/2019/04 Contractor (Daewoo ¡V Chun Wo ¡V Kwan Lee Joint
Venture) |
Site Agent |
Mr. Eric Wu |
9786 8630 |
-- |
Environmental Officer |
Mr. Sam Lam |
6178 3179 |
||
Contract No. ND/2019/05 Contractor (CRCC ¡V Paul Y. Joint Venture) |
Site Agent |
Mr. Darvin Lo |
9467 5891 |
-- |
Environmental Manager |
Mr. Pan Fong |
9436 9435 |
||
Environmental Officer |
Ms. Connie
Yuen |
6316 6931 |
||
Contract No. ND/2019/06 Contractor (New Concepts Engineering Development
Ltd.) |
Project
Manager |
Mr. Joe Cheng |
9861 0060 |
-- |
Environmental Officer |
Mr. Alex Choy |
6360 3236 |
||
Contract No. ND/2019/07 Contractor (China Road and Bridge Corporation) |
Site Agent |
Mr. Mac Chow |
9169 9567 |
-- |
Environmental Manager |
Mr. K. M. Lui |
5113 8223 |
Summary of
Construction Works Undertaken During Reporting Month
2.9
The major site activities undertaken in the
reporting month are shown in Table 2.3.
Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract No. |
Site Activities (August 2025) |
ND/2019/01 |
(a)
Drainage
works, watermain works, sheet piling and slope works in
Portion 1a (b)
Site
formation, watermain works, ELS construction, drainage works, sewage works,
backfilling and road works in Portion 1c (c)
Site
formation, construction of subway, drainage works, road works, soil nail and
slope works in Portion 2 (d)
HAC soil treatment and watermain
works in
Portion 3 (e)
UU works,
site formation, watermain works and drainage works in
Portion 5 (f)
Backfilling,
drainage works, watermain works, slope works, road works, district cooling
system and UU works in Portion 6a and 9c (g)
Operation
of HAC soil treatment facility in Portion 6b (h)
Excavation,
watermain works, sewage works, road works (UU) and drainage works in Portion
7 (i)
Road works, RC structure
works, drainage works, watermains works, backfilling, planting, metal works,
slope works and E&M works in Portion 8a (j)
Ground treatment,
grouting, watermain construction, ELS construction and RC structure works in
Portion 8b (k)
Sheet
piling, excavation, road works, drainage works, watermain works and district
cooling system in Portion 9b (l)
Drainage works and
watermain works in Portion 11b (m) Stockpile of soil in
Portion 13 |
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and Fill of Slope (e)
Sheet Piling (f)
Pipe
Jacking (g)
Pipe laying and bedding (h)
Grouting |
ND/2019/03 |
All
construction activities with significant environmental impact have been
substantially completed in April 2024 and all outstanding works with
defect rectification have also been completed on 28 March 2025. |
ND/2019/04 |
(a)
Back Filling (b)
Excavation (c)
Grouting (d)
Road works (e)
Formwork and Scaffolding Erection (f)
Rebar Fixing and ELS (g)
Backfilling (h)
Concreting (i)
MIC |
ND/2019/05 |
(a)
South
Team -
BBI
Toilet ¡V ABWF and installation bio treatment plant were in progress. -
BBI
Toilet ¡V Dwarf Wall construction was 70% completed. -
Lift LT01
¡V Lift installation was completed. Testing in progress. -
Road D400
¡V TTA-469 implemented on 20 July 2025. -
ADS21 PC1
¡V Sheetpiling works in progress. -
ADS21 PC2
¡V Protective measures for water main and trial pits for CLP132kV in progress. -
DS11 ¡V Sheetpiling for footing construction was in progress. -
D2-02 ¡V
Watermain laying for fire hydrant was in progress. -
E2-03 ¡V
Outfall construction was in progress. -
E3-01 ¡V
Removal of temporary working platform was still in progress. -
E4
Retaining Wall ¡V Temporary ramp to Bridge E4 was completed on 8 August 2025. -
E4 Ramp Utrough Bay 17~21 ¡V Stem walls were all completed up to
bottom of profile barrier. -
FW56 Bay
22~25 ¡V Stem walls were in progress. -
Noise
barrier NB109 and NB70 A.
Northbound
¡V Installation of concrete profile barrier at NB109 Bay 1~4 was in progress. B.
Southbound
¡V TTA-452 was implemented on 9 July 2025. Construction of remaining NB70
foundation shall resume after implementation of TTA-488. -
Noise
barrier NB69 and NB68 A.
NB69 ¡V
Bay 1~2a stem wall was completed. B.
NB68 ¡V
Bay 7 stem wall was in progress. ELS for Bay was completed and sheet piling
for Bay 1~5 was in progress. -
Noise
barrier NB 108 A.
Additional
trial pits required by WSD were completed. B.
TCSS
ducting and cables were found in conflict with the piling works. Cable
slewing was in progress. -
Remaining part of existing
sign gantry FADS8 was removed on 6 August 2025. Noise Barrier NB29 Trough Bay
1-23 A.
Footing
is 85% completed B.
Wall
(exclude parapet) is 80% completed. Parapet section will cast after
backfilling to formation. -
Noise barrier NB 30 A.
Bay 1 to
bay 20 blinding completed. B.
RC from
bay 1 to bay 7, & bay 15 to bay 20 completed & bay 10,13 & 14 in
progress. -
Noise barrier NB 77 C.
NB77 pile
cap completed, wall construction in progress. -
Sign Gantry A.
11 out of
20 Columns fabrication were completed. 10 Columns were installed. B.
4 out of
11 Mid Chords fabrication were completed. DS21B mid chord was in progress. C.
4 out of
11 sign gantries were installed on site. D.
Installation
of DS21A was completed on 8 August 2025. -
Fabrication
of Noise Barrier ¡V 36% of overall noise barrier columns were
completed. Fabrication of NB30 noise barrier column was in progress. (b)
North
Team -
C1-03
catch pit & manhole construction in progress. D2-01 & B2-03
completed. -
D1-01,
E2-01, C1-02 & C2-01 watermain works & pillar box for viaduct
completed. D1-04 in progress. -
Backfilling
of B2-03, B2-01, C1-01b & D2-01 in progress. -
JCR:
Construction of new central median & ducting works for traffic signal
& road light were completed of 100%. -
JCR &
Tong Hang Village J/O improvement works (FS 25): slope works 98 % completed. -
JCR &
Tong Hang Village J/O (near bus-stop) : Ducting works for traffic signal
& road light was in progress (100 % completed). -
JCR near
F63 ¡Vslope feature construction works completed. Street furniture in
progress. -
JCR
resurfacing in progress (40% completed) (c)
Bridges
and Structures -
Dismantle of LG completed. -
Installation of parapet
and central median for bridge in progress. -
Installation of fire
hydrant in progress. Fire hydrant at pier C2-01,C3-03 completed. -
Reinstate of lifting tower
NF83A in progress. -
Installation of movement
joint E1-04 in progress. Total 8 of 20 MJ installation completed. -
Water
proofing on bridge deck in progress, bridge D1, E1, C4R, C3R, C2R, C4L, C3L,
C2L completed. -
Asphalt
paving on the deck in progress, base course of bridge D1, E1, C4R, C3R, C2R,
C4L, C3L, C2L completed. -
Wearing
course pavement on the deck in progress. -
Installation
of railing and noise barrier on bridge deck in progress. -
E3 &
D2 external tendon in progress. |
ND/2019/06 |
The construction phase was completed and
handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 3 (b)
C&D waste disposal at Portion 2
and 4 (c)
Waterworks at Portion 3 |
Construction Programme
2.10 Copies of Contractors¡¦ construction programmes are provided in Appendix A.
Status of Environmental Licences,
Notifications and Permits
2.11
A summary of the relevant permits, licences, and/or notifications on environmental protection
for this Project is presented in Table
2.4.
Table 2.4 Status
of Environmental Licences, Notifications and Permits