Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
Contract No. |
Site Activities (July
2025) |
ND/2019/01 |
(a)
Drainage
works, watermain works,
sheet piling and slope works
in Portion 1a (b)
Site
formation, watermain works, ELS construction, sewage
works, backfill and road works in
Portion 1c (c)
Site
formation, construction of subway, drainage
works, road
works, soil nail and slope work in Portion 2 (d)
HAC soil treatment and watermain works in Portion 3 (e)
Site
formation, watermain works and drainage works in Portion 5 (f)
Backfilling,
drainage works, watermain works, slope works, road works
and district cooling system in Portion 6a (g)
Operation
of HAC soil
treatment facility in Portion 6b (h)
Excavation, watermain works, sewage works, road works (UU)
and drainage works in Portion 7 (i)
Road works, RC structure works, drainage works, watermain
works, backfilling,
planting, metal works, slope works and E&M works in Portion 8a (j)
Ground Treatment, grouting,
watermain construction and
ELS construction and RC structure works in
Portion 8b (k)
Sheet
piling, excavation, road works, drainage works, watermain works and district cooling system in
Portion 9b (l)
Drainage works in Portion
10b (m)
Drainage works and
watermain works in Portion 11b (n)
Stockpile of soil
in Portion 13 |
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and Fill of Slope (e)
Sheet Piling (f)
Pipe
Jacking (g)
Pipe laying and bedding (h)
Grouting |
ND/2019/03 |
All
construction activities with significant environmental impact have been
substantially completed in
April 2024 and all outstanding works with defect rectification have also been
completed on 28 March 2025. |
ND/2019/04 |
(a)
Back Filling (b)
Excavation (c)
Grouting (d)
Road works (e)
Formwork and Scaffolding Erection (f)
Rebar Fixing and ELS (g)
Backfilling (h)
Concreting (i)
MIC |
ND/2019/05 |
(a)
South
Team -
BBI
Toilet ¡V ABWF and installation bio treatment plant were in progress. -
BBI
Toilet ¡V Dwarf Wall construction in progress. -
Lift LT01
¡V Lift installation was completed. Testing in progress. -
Road D400
¡V Site formation in progress for TTA-469. -
ADS21 PC1
¡V Trial pit in progress to locate the uncharted road light cable. -
ADS21 PC2
¡V Commencement of piling works was waiting for WSD¡¦s approval. -
D2-02 ¡V
Outfall construction completed. Watermain laying for fire hydrant in
progress. -
E2-03 ¡V
Outfall construction was in progress. -
E3-01 ¡V
Removal of temporary working platform was in progress -
E3-02 ¡V
Drainage system from pier to existing was completed. -
E4
Retaining Wall ¡V Stem wall was completed. Backfilling works in progress -
E4 Ramp
Utrough Bay 17~21 ¡V Footings were completed. Stem walls were 70% completed. -
FW56 Bay
22~25 ¡V Footings were completed. Stem walls were in progress. -
Noise
barrier NB109 and NB70 A.
Pavement
works along FLH Northbound was completed and TTA-456 was implemented on 20
June 2025. B.
Pavement
works along FLH Southbound was completed and TTA-452 was implemented on 9
July 2025. However, those pavement at NB109 Bay1-4 and NB70 Bay1-6 are
temporary only due to adverse weather has affected the SRT schedule. -
Noise
barrier NB69 and NB68 A.
NB69 ¡V
Bay 2a stem wall was completed. Bay 1 stem wall was in progress. B.
NB68 ¡V
Bay 7 footing was completed and its stem wall was in progress. -
Noise
barrier NB 29 Through Bay 1-23 A.
Footing
is 80% completed B.
Wall
(exclude parapet) is 70% completed. Parapet section will cast after
backfilling to formation. -
Noise barrier NB 30 A.
Bay 1 to
Bay 13, bay 15 to bay 20 blinding completed. B.
RC from
bay 1 to bay 5, & bay 16 to bay 20 completed & bay 6, 9 in progress. -
Noise barrier NB 77 A.
NB77 pile
cap completed, wall construction in progress. -
Sign Gantry A.
8 out of
20 Columns fabrication were completed. Fabrication of DS21A columns is in
progress. B.
3 out of
11 Mid Chords were completed. Fabrication of DS21A mid chord is in progress. C.
2 out of
11 sign gantries were completed and erected on site. D.
Installation
of DS20 was completed on 30 June 2025. E.
Installation
of FADS19 will be carried out by end of July 2025. -
Fabrication
of Noise Barrier ¡V 32% of overall noise barrier columns were completed.
Fabrication of NB28 noise barrier column is in progress. (b)
North
Team -
D2-01,
C1-03 & B2-03 catch pit & manhole construction in progress. B2-01
completed. -
D1-01,
E2-01, C1-02 & C2-01 watermain works & pillar box for viaduct
completed. D1-04 in progress. -
Backfilling
of B2-03, B2-01, C1-01b & D2-01 in progress. -
JCR:
Construction of new central median & ducting works for traffic signal
& road light were completed of 100%. -
JCR &
Tong Hang Village J/O improvement works (FS 25): slope works 98 % completed. -
JCR &
Tong Hang Village J/O (near bus-stop) : Ducting works for traffic signal
& road light was in progress (98 % completed). -
JCR near
F63 ¡Vslope feature construction works completed. Street furniture in
progress. -
JCR
resurfacing in progress (30% completed) (c)
Bridges
and Structures -
LG launched back to C1-01,
and the dismantle of LG in progress. -
Installation of parapet
and central median for bridge in progress -
Installation of fire
hydrant in progress. -
Reinstate of lifting tower
NF83A in progress. -
Installation of movement
joint C1-04a and C2-04a completed. Total 8 of 20 MJ installation completed. -
Water proofing on bridge
deck in progress, bridge D1, E1, C4R, C3R, C2R, C4L, C3L, C2L completed. -
Asphalt
paving on the deck in progress, base course of bridge D1, E1, C4R, C3R, C2R,
C4L, C3L, C2L completed. -
Wearing
course pavement on the deck in progress. -
Installation
of railing and noise barrier on bridge deck in progress. -
Construction
of the 2nd pour concrete of B1-01 diaphragm beam and remaining Bridge B1 deck
in progress. -
E2 &
D2 external tendon in progress. |
ND/2019/06 |
The construction phase was
completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 3 and 4 (b)
C&D waste disposal at Portion 2 and 4 (c)
Filling works at Portion 2 (d)
Construction of site haul road at Portion 4 (e)
Drainage works at Portion 1, 2, 3 and 4 (f)
Sewerage works at Portion 3 and 4 (g)
Construction
of noise barrier at Portion 4 (h)
Waterworks at Portion 1, 2, 3 and 4 |