Table IV Summary Table for Site Activities in the coming Three
Months
Contract No. |
Site Activities (August to October 2025) |
ND/2019/01 |
(a)
Drainage works, watermain
works, sheet piling, site formation and slope works in Portion 1a (b)
Site formation, watermain
works, ELS construction, sewage works, backfilling and road works in Portion
1c (c)
Site formation,
construction of subway, road works, drainage works, slope works and soil nail
in Portion 2 (d)
HAC soil treatment and watermain
works in Portion 3 (e)
Site formation, watermain
works and drainage works in Portion 5 (f)
Backfilling, drainage
works, watermains works, slope works, road works and ELS construction in
Portion 6a (g)
Operation of HAC treatment
facility in Portion 6b (h)
Excavation, drainage works,
watermain works, sewage works and road works in Portion 7 (i)
Road works, RC structure
works, drainage works, watermain works, backfilling, planting, metal works,
slope works and E&M works in Portion 8a (j)
Ground treatment, grouting,
watermain works, ELS construction and RC structure works in Portion 8b (k)
Sheet piling, excavation, road
works, drainage works, watermain works and district cooling system works in
Portion 9b (l)
Drainage works, sewerage
works, watermain works and road works in Portion 10b. (m)
Excavation, watermain
works, drainage works and road works in Portion 11b (n)
Stockpile of soil in
Portion 13 |
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and Fill of Slope (e)
Sheet Piling (f)
Pipe Jacking (g)
Pipe laying and bedding (h)
Grouting |
ND/2019/03 |
The
construction phase has been completed since 28 March 2025. |
ND/2019/04 |
(a)
Back Filling (b)
Excavation (c)
Grouting (d)
Road works (e)
Formwork and Scaffolding Erection (f)
Rebar Fixing and ELS (g)
Backfilling (h)
MIC |
ND/2019/05 |
(a)
Backfilling (b)
Drainage works (c)
Water works (d)
Ducting and Road works (e)
Slope works (f)
Segments erection (g)
ELS (h)
Wall construction |
ND/2019/06 |
The
construction phase has been completed and handed over to AFCD since 4 April
2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 3
and 4 (b)
C&D waste disposal at
Portion 2 and 4 (c)
Filling Works at Portion 2 (d)
Construction of site haul
road at Portion 4 (e)
Drainage works at Portion 1,
2, 3 and 4 (f)
Sewerage works at Portion
3 and 4 (g)
Construction of noise
barrier at Portion 4 (h)
Waterworks at Portion 1, 2,
3 and 4 |