Table IV       Summary Table for Site Activities in the coming Three Months

Contract No.

Site Activities (April to June 2025)

ND/2019/01

(a)          Drainage works, watermain works, sheet piling, site formation and slope works in Portion 1a

(b)         Watermain works in Portion 1b

(c)          Site formation, drainage works, watermain works, construction of noise barrier, road lighting works, ELS construction, sewage works, backfilling and road works in Portion 1c

(d)         Site formation, construction of subway, road works, drainage works, slope works and soil nail in Portion 2

(e)          HAC soil treatment, site formation, excavation, road works, slope work, drainage works, watermain works and soil nail in Portion 3

(f)          Sewage works, excavation, backfilling, road works and construction of public lighting in Portion 5

(g)         Drainage works, backfilling, road works, watermains works, construction of retaining wall, slope works, district cooling system works and road lighting works in Portion 6a

(h)         Operation of HAC treatment facility in Portion 6b

(i)           Sheet piling, excavation, stockpile of soil, drainage works, watermain works and road works in Portion 7

(j)           Road pavement construction, RC construction of fresh water reservoir, backfilling works, drainage works, watermain works, soil nail, planting and metal works in Portion 8a

(k)         Trenchless works, watermain works, ground treatment, grouting, ELS construction and chamber construction in Portion 8b

(l)           Sheet piling, ELS construction, road works, drainage works, watermain works, district cooling system works, grouting works and public lighting in Portion 9b

(m)       Backfilling in Portion 9c

(n)         Sewage works, drainage works, road works, backfilling, excavation and sheet piling in Portion 10b

(o)         Site formation, excavation, drainage works, roadworks and watermain works in Portion 11b

(p)         Stockpile of soil in Portion 13

ND/2019/02

(a)            Backfilling

(b)           Excavation

(c)            Concreting

(d)           Cut and Fill of Slope

(e)            Sheet Piling

(f)            Pipe Jacking

(g)           Pipe laying and bedding

(h)           Grouting

ND/2019/03

The construction phase has been completed since 28 March 2025.

ND/2019/04

(a)           Pile Cap

(b)           Back Filling

(c)           Excavation

(d)           Grouting

(e)           Road works

(f)            Formwork and Scaffolding Erection

(g)           Rebar Fixing and ELS

(h)           Backfilling

(i)            S960 Delivery

ND/2019/05

(a)        Backfilling

(b)       Drainage works

(c)        Water works

(d)       Ducting and Road works

(e)        Slope works

(f)        Segments erection

(g)       ELS

(h)       Wall construction

ND/2019/06

The construction phase has been completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)        Road works at Portion 1, 3 and 4

(b)        C&D waste disposal at Portion 2 and 4

(c)        Filling Works at Portion 2

(d)        Construction of site haul road at Portion 4

(e)        Drainage works at Portion 1, 2, 3 and 4

(f)         Sewerage works at Portion 3 and 4

(g)        Construction of noise barrier at Portion 4

(h)        Waterworks at Portion 1, 2, 3 and 4