Table IV Summary Table for Site Activities in the coming Three
Months
Contract No. |
Site Activities (April to June 2025) |
ND/2019/01 |
(a)
Drainage works, watermain
works, sheet piling, site formation and slope works in Portion 1a (b)
Watermain works in Portion
1b (c)
Site formation, drainage
works, watermain works, construction of noise barrier, road lighting works,
ELS construction, sewage works, backfilling and road works in Portion 1c (d)
Site formation,
construction of subway, road works, drainage works, slope works and soil nail
in Portion 2 (e)
HAC soil treatment, site
formation, excavation, road works, slope work, drainage works, watermain
works and soil nail in Portion 3 (f)
Sewage works, excavation,
backfilling, road works and construction of public lighting in Portion 5 (g)
Drainage works, backfilling,
road works, watermains works, construction of retaining wall, slope works,
district cooling system works and road lighting works in Portion 6a (h)
Operation of HAC treatment
facility in Portion 6b (i)
Sheet piling, excavation,
stockpile of soil, drainage works, watermain works and road works in Portion
7 (j)
Road pavement
construction, RC construction of fresh water reservoir, backfilling works,
drainage works, watermain works, soil nail, planting and metal works in
Portion 8a (k)
Trenchless works, watermain
works, ground treatment, grouting, ELS construction and chamber construction in
Portion 8b (l)
Sheet piling, ELS
construction, road works, drainage works, watermain works, district cooling
system works, grouting works and public lighting in Portion 9b (m)
Backfilling in Portion 9c (n)
Sewage works, drainage
works, road works, backfilling, excavation and sheet piling in Portion 10b (o)
Site formation,
excavation, drainage works, roadworks and watermain works in Portion 11b (p)
Stockpile of soil in
Portion 13 |
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and Fill of Slope (e)
Sheet Piling (f)
Pipe Jacking (g)
Pipe laying and bedding (h)
Grouting |
ND/2019/03 |
The construction
phase has been completed since 28 March 2025. |
ND/2019/04 |
(a)
Pile Cap (b)
Back Filling (c)
Excavation (d)
Grouting (e)
Road works (f)
Formwork and Scaffolding Erection (g)
Rebar Fixing and ELS (h)
Backfilling (i)
S960 Delivery |
ND/2019/05 |
(a)
Backfilling (b)
Drainage works (c)
Water works (d)
Ducting and Road works (e)
Slope works (f)
Segments erection (g)
ELS (h)
Wall construction |
ND/2019/06 |
The
construction phase has been completed and handed over to AFCD since 4 April
2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 3
and 4 (b)
C&D waste disposal at Portion
2 and 4 (c)
Filling Works at Portion 2 (d)
Construction of site haul
road at Portion 4 (e)
Drainage works at Portion 1,
2, 3 and 4 (f)
Sewerage works at Portion
3 and 4 (g)
Construction of noise
barrier at Portion 4 (h)
Waterworks at Portion 1, 2,
3 and 4 |