Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
Contract No. |
Site Activities (May
2025) |
ND/2019/01 |
(a)
Drainage
works, watermain works,
sheet piling and slope works
in Portion 1a (b)
Site
formation, watermain works, ELS construction, sewage
works, backfill and road works in
Portion 1c (c)
Site
formation, construction of subway, drainage
works, road
works, soil nail and slope work in Portion 2 (d)
HAC soil treatment, watermain works,
drainage works and
sheet piles in Portion 3 (e)
Site
formation, watermain works and drainage works in Portion 5 (f)
Backfilling,
drainage works, watermain works, slope works, road works
and district cooling system in Portion 6a (g)
Operation
of HAC soil
treatment facility in Portion 6b (h)
Excavation, watermain works, sewage works, road works and
drainage works in Portion 7 (i)
Road works, RC structure works, drainage works, watermain
works, backfilling,
planting, metal works, slope works and E&M works in Portion 8a (j)
Ground Treatment, trenchless work, grouting,
watermain construction and
ELS construction in Portion 8b (k)
Sheet
piling, excavation, drainage works, watermain works and district cooling system in
Portion 9b (l)
No activity in Portion 11b
this month (m)
Stockpile of soil
in Portion 13 |
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and Fill of Slope (e)
Sheet Piling (f)
Pipe
Jacking (g)
Pipe laying and bedding (h)
Grouting |
ND/2019/03 |
All
construction activities with significant environmental impact have been
substantially completed in
April 2024 and all outstanding works with defect rectification have also been
completed on 28 March 2025. |
ND/2019/04 |
(a)
Back Filling (b)
Excavation (c)
Grouting (d)
Road works (e)
Formwork and Scaffolding Erection (f)
Rebar Fixing and ELS (g)
Backfilling (h)
S960
Delivery (i)
Concreting |
ND/2019/05 |
(a)
South
Team -
BBI
Toilet ¡V ABWF and installation bio treatment plant are in progress. -
BBI
Toilet ¡V Dwarf Wall excavation to formation in progress. -
Lift LT01
¡V Lift installation is in progress. -
FS01a ¡V
Backfilling completed. Site being setup for sign gantry DS20 assembly. -
D400 ¡V
Road drainage construction and site formation are in progress for TTA-469. -
ADS21 PC1
¡V TTA-455 implemented on 29 April 2025. Site Clearance in progress. -
ADS21 PC2
¡V Site clearance and UU slewing completed. Waiting for WSD¡¦s approval for
commencement of piling works. -
E2-03 ¡V
Slope reinstatement completed and all sheetpiles were extracted. Outfall
construction is in progress. -
E3-02 ¡V
Watermain laying to pier is completed. -
E4
Retaining Wall ¡V Stem wall is 75% completed. -
E4 Ramp
Utrough Bay 17~21 ¡V Footing is 80% completed. Bay 17 east wall construction
is completed and Bay 18 east wall is in progress. -
FW56 Bay
22~25 ¡V Footings are 50% completed. Excavation for Bay 24~25 are in progress. -
Noise
barrier NB109 Bay 5~19 A.
65 out of
81 noise barrier columns are installed. Installation of concrete profile
barrier is completed from Bay 5~19. B.
Bay 1~4
2nd cast of stem wall is completed. -
Noise
barrier NB70 A.
Bay 1 to
6 ¡V Backfilling subbase layer in progress. -
Noise
barrier NB69 A.
Bay 1, 2a
¡V Excavation is completed. Construction of footing is in progress. -
Noise
barrier NB 29 Through Bay 1-23 A.
Footing
is 75% completed B.
Wall
(exclude parapet) is 65% completed. Parapet section will cast after
backfilling to formation. -
Noise barrier NB 30 A.
Pre-bored
Socket H pile construction (211/211 nos) completed. B.
RC from
bay 17 & 20 completed & bay 13 to 16 in progress. -
Noise barrier NB 77 A.
ELS works
for NB77 footing in progress. -
Fabrication
of Sign Gantry ¡V 5 out of 20 Columns are completed. 6 columns and DS20 Mid
Chord are under fabrication. -
Fabrication
of Noise Barrier ¡V Fabrication of NB27 and NB31 noise barrier columns are
completed. NB110, NB28 and NB27a fabrication are in progress. (b)
North
Team -
Reinstatement
works & footpath in progress in C4-02 (HD) -
C2-02,
B2-01 & B2-02 catch pit & manhole construction in progress. -
D1-01,
E2-01, C1-02 & C2-01 watermain works & pillar box for viaduct in
progress. -
Backfilling
of B2-02, B2-03, C1-01b & D2-01 in progress. -
JCR: Construction
of new central median & ducting works for traffic signal & road light
were completed of 100%. -
JCR &
Tong Hang Village J/O improvement works (FS 25): slope works 98 % completed. -
JCR &
Tong Hang Village J/O (near bus-stop) : Ducting works for traffic signal
& road light was in progress (98 % completed). -
JCR near
F63 ¡Vslope feature construction works completed. (c)
Bridges
and Structures -
LG launched back to C1-01,
and the dismantle of LG in progress. -
Installation of parapet
and central median for bridge E3, E2 in progress -
Installation of deck void
drainage at Bridge B2 in progress. -
Reinstate of lifting tower
NF83A in progress. -
Installation of movement
joint C3-04a and C1-04a completed. Total 6 of 20 MJ installation completed. -
Water proofing on bridge
deck in progress, bridge D1, E1, C4R, C3R, C2R completed. -
Asphalt paving on the deck
in progress, base course of bridge E1, D1, C4R, C3R, C2R completed. -
Installation of railing
and noise barrier on bridge deck in progress. -
The 1st pour concrete of
B1-01 diaphragm beam casted on 9-May-2025. (d)
Form Traveler -
Parapet
skin installation at D2 bridge in progress. -
External
tendon at E2 bridge in progress. |
ND/2019/06 |
The construction phase was
completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 3 and 4 (b)
C&D waste disposal at Portion 2 and 4 (c)
Filling works at Portion 2 (d)
Construction of site haul road at Portion 4 (e)
Drainage works at Portion 1, 2, 3 and 4 (f)
Sewerage works at Portion 3 and 4 (g)
Construction
of noise barrier at Portion 4 (h)
Waterworks at Portion 1, 2, 3 and 4 |