Table IV       Summary Table for Site Activities in the coming Three Months

Contract No.

Site Activities (June to August 2025)

ND/2019/01

(a)          Drainage works, watermain works, sheet piling, site formation and slope works in Portion 1a

(b)         Site formation, watermain works, ELS construction, sewage works, backfilling and road works in Portion 1c

(c)          Site formation, construction of subway, road works, drainage works and slope works in Portion 2

(d)         HAC soil treatment, drainage works, watermain works and sheet piling in Portion 3

(e)          Site formation, watermain works and drainage works in Portion 5

(f)          Backfilling, drainage works, watermains works, slope works and road works in Portion 6a

(g)         Operation of HAC treatment facility in Portion 6b

(h)         Excavation, drainage works, watermain works, sewage works and road works in Portion 7

(i)           Road works, RC structure works, drainage works, watermain works, backfilling, planting, metal works, slope works and E&M works in Portion 8a

(j)           Ground treatment, trenchless works, grouting, watermain works, ELS construction and RC structure works (reinforced concrete) in Portion 8b

(k)         Sheet piling, excavation, drainage works, watermain works and district cooling system works in Portion 9b

(l)           No activities in upcoming month in Portion 11b

(m)       Stockpile of soil in Portion 13

ND/2019/02

(a)            Backfilling

(b)           Excavation

(c)            Concreting

(d)           Cut and Fill of Slope

(e)            Sheet Piling

(f)            Pipe Jacking

(g)           Pipe laying and bedding

(h)           Grouting

ND/2019/03

The construction phase has been completed since 28 March 2025.

ND/2019/04

(a)           Back Filling

(b)           Excavation

(c)           Grouting

(d)           Road works

(e)           Formwork and Scaffolding Erection

(f)            Rebar Fixing and ELS

(g)           Backfilling

ND/2019/05

(a)        Backfilling

(b)       Drainage works

(c)        Water works

(d)       Ducting and Road works

(e)        Slope works

(f)        Segments erection

(g)       ELS

(h)       Wall construction

ND/2019/06

The construction phase has been completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)        Road works at Portion 1, 3 and 4

(b)        C&D waste disposal at Portion 2 and 4

(c)        Filling Works at Portion 2

(d)        Construction of site haul road at Portion 4

(e)        Drainage works at Portion 1, 2, 3 and 4

(f)         Sewerage works at Portion 3 and 4

(g)        Construction of noise barrier at Portion 4

(h)        Waterworks at Portion 1, 2, 3 and 4