Table IV Summary Table for Site Activities in the coming Three
Months
Contract No. |
Site Activities (June to August 2025) |
ND/2019/01 |
(a)
Drainage works, watermain
works, sheet piling, site formation and slope works in Portion 1a (b)
Site formation, watermain works,
ELS construction, sewage works, backfilling and road works in Portion 1c (c)
Site formation,
construction of subway, road works, drainage works and slope works in Portion
2 (d)
HAC soil treatment,
drainage works, watermain works and sheet piling in Portion 3 (e)
Site formation, watermain
works and drainage works in Portion 5 (f)
Backfilling, drainage
works, watermains works, slope works and road works in Portion 6a (g)
Operation of HAC treatment
facility in Portion 6b (h)
Excavation, drainage
works, watermain works, sewage works and road works in Portion 7 (i)
Road works, RC structure
works, drainage works, watermain works, backfilling, planting, metal works,
slope works and E&M works in Portion 8a (j)
Ground treatment,
trenchless works, grouting, watermain works, ELS construction and RC
structure works (reinforced concrete) in Portion 8b (k)
Sheet piling, excavation,
drainage works, watermain works and district cooling system works in Portion
9b (l)
No activities in upcoming
month in Portion 11b (m)
Stockpile of soil in
Portion 13 |
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut
and Fill of Slope (e)
Sheet
Piling (f)
Pipe
Jacking (g)
Pipe
laying and bedding (h)
Grouting |
ND/2019/03 |
The
construction phase has been completed since 28 March 2025. |
ND/2019/04 |
(a)
Back
Filling (b)
Excavation (c)
Grouting (d)
Road
works (e)
Formwork
and Scaffolding Erection (f)
Rebar
Fixing and ELS (g)
Backfilling |
ND/2019/05 |
(a)
Backfilling (b)
Drainage works (c)
Water works (d)
Ducting and Road works (e)
Slope works (f)
Segments erection (g)
ELS (h)
Wall construction |
ND/2019/06 |
The construction phase has been completed and
handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road
works at Portion 1, 3 and 4 (b)
C&D
waste disposal at Portion 2 and 4 (c)
Filling
Works at Portion 2 (d)
Construction
of site haul road at Portion 4 (e)
Drainage
works at Portion 1, 2, 3 and 4 (f)
Sewerage
works at Portion 3 and 4 (g)
Construction
of noise barrier at Portion 4 (h)
Waterworks
at Portion 1, 2, 3 and 4 |