Table 10.2       Observations and Recommendations during Site Audits

Parameters

Date

Observations and Recommendations

Follow-up

Contract No.: ND/2019/01

 

--

--

--

--

Contract No.: ND/2019/02

Water Quality

08/10/2025

Drainage system should be well maintained to avoid surface runoff exceeds site boundary at CH1680.

Item was remarked as 251015-R01. Follow-up action is needed to be reviewed.

15/10/2025

Improvement/Rectification was observed during follow-up audit session on 22 October 2025.

30/09/2025

Used bentonite slurries should be collected and stored properly.

Item was remarked as 251008-R03. Follow-up action is needed to be reviewed.

08/10/2025

Improvement/Rectification was observed during follow-up audit session on 15 October 2025.

Ecology

30/09/2025

Silt curtain should be maintained properly and regularly.

Item was remarked as 251008-R03. Follow-up action is needed to be reviewed.

08/10/2025

Item was remarked as 251015-R02. Follow-up action is needed to be reviewed.

15/10/2025

Item was remarked as 251022-R01. Follow-up action is needed to be reviewed.

22/10/2025

Item was remarked as 251028-R01. Follow-up action is needed to be reviewed.

28/10/2025

Follow-up action is needed to be reported in the following month.

Waste/Chemical Management

30/09/2025

Drip tray for chemical/fuel containers at CH1680 should be provided.

Improvement/Rectification was observed during follow-up audit session on 8 October 2025.

Contract No.: ND/2019/04

Water Quality

02/10/2025

Sand bag bunds should be supplemented to avoid surface runoff entering Ng Tung River.

Item was remarked as 251009-R01. Follow-up action is needed to be reviewed.

09/10/2025

Improvement/Rectification was observed during follow-up audit session on 16 October 2025.

Waste / Chemical Management

02/10/2025

General refuse should be disposed of regularly and properly.

Improvement/Rectification was observed during follow-up audit session on 9 October 2025.

09/10/2025

General refuse should be disposed of regularly and properly.

Improvement/Rectification was observed during follow-up audit session on 16 October 2025.

Air Quality

09/10/2025

Stockpile of dusty material should be covered by impervious sheeting properly or water-sprayed regularly as dust suppression.

Item was remarked as 251016-R01. Follow-up action is needed to be reviewed.

16/10/2025

Item was remarked as 251021-R01. Follow-up action is needed to be reviewed.

21/10/2025

Item was remarked as 251030-R01. Follow-up action is needed to be reviewed.

30/10/2025

Follow-up action is needed to be reported in the following month.

21/10/2025

Dust suppression measures should be enhanced.

Improvement/Rectification was observed during follow-up audit session on 30 October 2025.

Ecology

02/10/2025

2m high dull green barrier along the 10m buffer zone should be erected and maintained properly.

Improvement/Rectification was observed during follow-up audit session on 9 October 2025.

16/10/2025

2m high dull green barrier along the 10m buffer zone should be erected and maintained properly.

Item was remarked as 251021-R02. Follow-up action is needed to be reviewed.

21/10/2025

Improvement/Rectification was observed during follow-up audit session on 30 October 2025.

Contract No.: ND/2019/05

Waste/Chemical Management

20/10/2025

Drip tray for chemical/fuel containers should be provided.

Improvement/Rectification was observed during follow-up audit session on 28 October 2025.

Air Quality

06/10/2025

Stockpile of dusty material should be covered by impervious sheeting properly.

Improvement/Rectification was observed during follow-up audit session on 13 October 2025.

20/10/2025

NRMM labels on the regulated machines should be displayed properly.

Improvement/Rectification was observed during follow-up audit session on 28 October 2025.

Contract No.: ND/2019/07

 

--

--

--

--