Table 2.3     Summary Table for Major Site Activities in the Reporting Month

Contract No.

Site Activities (October 2025)

ND/2019/01

(a)          Drainage works and watermain works in Portion 1a

(b)         Site formation, watermain works, ELS construction, drainage works, sewage works, backfilling and road works in Portion 1c

(c)          Site formation, construction of subway, drainage works, road works, soil nail and slope works in Portion 2

(d)         HAC soil treatment, watermain works and UU works in Portion 3

(e)          UU works, site formation and watermain works in Portion 5

(f)          Backfilling, drainage works, watermain works, slope works, road works, district cooling system and UU works in Portion 6a and 9c

(g)         Operation of HAC soil treatment facility in Portion 6b

(h)         Excavation, watermain works, sewage works, road works (UU) and smart lighting in Portion 7

(i)           Road works, RC structure works, drainage works, watermains works, backfilling, planting, metal works, slope works and E&M works in Portion 8a

(j)           Ground treatment, grouting, watermain construction, ELS construction and RC structure works in Portion 8b

(k)         Excavation, road works, drainage works, watermain works, district cooling system and smart lighting in Portion 9b

(l)           Drainage works, watermain works and road works in Portion 11b

(m)       Stockpile of soil in Portion 13

ND/2019/02

(a)           Backfilling

(b)           Excavation

(c)            Concreting

(d)           Cut and Fill of Slope

(e)            Sheet Piling

(f)            Pipe Jacking

(g)           Pipe laying and bedding

(h)           Grouting

ND/2019/03

All construction activities with significant environmental impact have been substantially completed in April 2024 and all outstanding works with defect rectification have also been completed on 28 March 2025.

ND/2019/04

(a)           Back Filling

(b)           Excavation

(c)           Grouting

(d)           Road works

(e)           E&M works

(f)            Formwork and Scaffolding Erection

(g)           Rebar Fixing and ELS

(h)           Concreting

(i)            MIC

(j)            Noise barrier installation

ND/2019/05

(a)          South Team

-          BBI Toilet ¡V ABWF and installation bio treatment plant were in progress.

-          BBI Toilet ¡V Dwarf Wall construction was 70% completed.

-          Lift LT01 ¡V Lift installation was completed.

-          Road D400 ¡V Road works for TTA-488 in progress. Tentative implementation date is 24 October 2025.

-          ADS21 PC1 ¡V Excavation completed and footing construction was in progress.

-          ADS21 PC2 ¡V Mini-piles construction was in progress.

-          DS11 ¡V Sheetpiling for footing construction was in progress.

-          D2-02 ¡V Watermain laying for fire hydrant was in progress.

-          E3-01 ¡V Backfilling for slope reinstatement was in progress.

-          E4 Retaining Wall ¡V Backfilling and road drainage were in progress.

-          E4 Ramp Utrough Bay 17~21 ¡V All profile barriers were completed.

-          FW56 Bay 22~25 ¡V All profile barriers were completed.

-          Noise barrier NB109 and NB70

A.         Northbound ¡V Installation of concrete profile barrier at NB109 Bay 1~4 was completed. Pavement was also reinstated.

B.          Southbound ¡V Tentative implementation date of TTA-488 shall be 24 October 2025.

-          Noise barrier NB69 and NB68

A.         NB68 ¡V Bay 6 stem wall was completed and construction of Bay 5 stem wall was in progress. Excavation of Bay 1 and 2 was completed and construction of their footings were in progress.

-          Noise barrier NB 108

A.         Piling works were commenced on 2 September 2025. 12 out of 48 piles were completed.

B.          An uncharted reinforced concrete was foundation in Bay 4. Design review was in progress.

C.          Sheetpilng works from Bay 9 to 17 were in progress.

-          Noise barrier NB 66

A.         TTA492 for construction of NB66 was implemented on 17 September 2025.

B.          Additional trial pits to locate abandoned pilecap were carried on 22 September 2025.

-          Remaining part of existing sign gantry FADS8 was removed on 6 August 2025. Noise Barrier NB29 Trough Bay 1-23

A.         Footing 100% completed

B.          Wall (exclude parapet) is 100% completed. Parapet & backfilling & drainage work in progress.

-          Noise barrier NB 30

A.         Drainage work & backfilling work in progress.

-          Noise barrier NB 77

B.          NB77 pile cap completed, abutment wall construction completed.

-          Sign Gantry

A.         15 out of 20 columns fabrication were completed. 11 Columns were installed.

B.          6 out of 11 mid chords fabrication were completed. FADS11 mid chord was completed.

C.          5 out of 11 sign gantries were installed on site.

D.         Installation of DS21B was completed on 10 September 2025.

-         Fabrication of Noise Barrier ¡V 40% of overall noise barrier columns were completed. Fabrication of NB30 noise barrier column was in progress.

(b)         North Team

-          C1-03, C4-03 & D1-02 catch pit & manhole construction in progress.

-          D1-01, E2-01, C1-02 & C2-01 watermain works & pillar box for viaduct completed. D1-04 in progress.

-          Backfilling of B2-03, B2-01, B1-02A & D2-01 in progress.

-          JCR: Construction of new central median & ducting works for traffic signal & road light were completed of 100%.

-          JCR & Tong Hang Village J/O improvement works (FS 25): slope works 98 % completed.

-          JCR & Tong Hang Village J/O (near bus-stop) : Ducting works for traffic signal & road light was in progress (100 % completed).

-          JCR near F63 ¡Vslope feature construction works completed. Street furniture in progress.

-          JCR resurfacing in progress (100% completed)

(c)          Bridges and Structures

-          Installation of parapet and central median for bridge in progress. Parapet construction at bridge E2, E3, E4, D2 completed.

-          Fire hydrant at pier C3-02 completed, installation of fire hydrant at pier E2-01&D2-02 in progress.

-          Reinstate of lifting tower NF83A in progress. Water proofing completed.

-          Installation of movement joint E3-05 completed, total 11 of 20 MJ installation completed.

-          Water proofing on bridge deck in progress, bridge D1, E1, E2, E4, C4R, C3R, C2R, C4L, C3L, C2L completed.

-          Asphalt paving on the deck in progress, base course of bridge D1, E1, E2, E3, C4R, C3R, C2R, C4L, C3L, C2L completed.

-          Wearing course pavement on the deck in progress.

-          HMFC pavement at C2R and C3R completed.

-          Noise barrier NB28 at bridge E3 completed.

-          Installation of railing on bridge deck in progress.

-          E2 & D2 external tendon completed, & E3 in progress

ND/2019/06

The construction phase was completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)        Road works at Portion 3

(b)        C&D waste disposal at Portion 1 and 3