Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
|
Contract No. |
Site Activities (October
2025) |
|
ND/2019/01 |
(a)
Drainage
works and
watermain works in Portion 1a (b)
Site
formation, watermain works, ELS construction, drainage works, sewage works,
backfilling and road works in Portion 1c (c)
Site
formation, construction of subway, drainage works, road works, soil nail and
slope works in
Portion 2 (d)
HAC soil treatment, watermain works and
UU works in Portion 3 (e)
UU works,
site formation and
watermain works in
Portion 5 (f)
Backfilling,
drainage works, watermain works, slope works, road works, district cooling
system and UU works in
Portion 6a and 9c (g)
Operation
of HAC soil
treatment facility in Portion 6b (h)
Excavation,
watermain works, sewage works, road works (UU) and smart
lighting in Portion 7 (i)
Road works, RC structure
works, drainage works, watermains works, backfilling, planting, metal works,
slope works and E&M works in
Portion 8a (j)
Ground treatment,
grouting, watermain construction, ELS construction and RC structure works in Portion 8b (k)
Excavation,
road works, drainage works, watermain works, district cooling system and
smart lighting in Portion 9b (l)
Drainage works, watermain
works and road works in Portion 11b (m)
Stockpile of soil
in Portion 13 |
|
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and Fill of Slope (e)
Sheet Piling (f)
Pipe
Jacking (g)
Pipe laying and bedding (h)
Grouting |
|
ND/2019/03 |
All
construction activities with significant environmental impact have been
substantially completed in
April 2024 and all outstanding works with defect rectification have also been
completed on 28 March 2025. |
|
ND/2019/04 |
(a)
Back Filling (b)
Excavation (c)
Grouting (d)
Road works (e)
E&M
works (f)
Formwork and Scaffolding Erection (g)
Rebar Fixing and ELS (h)
Concreting (i)
MIC (j)
Noise barrier installation |
|
ND/2019/05 |
(a)
South
Team -
BBI
Toilet ¡V ABWF and installation bio treatment plant were in progress. -
BBI
Toilet ¡V Dwarf Wall construction was 70% completed. -
Lift LT01
¡V Lift installation was completed. -
Road D400
¡V Road works for TTA-488 in progress. Tentative implementation date is 24
October 2025. -
ADS21 PC1
¡V Excavation completed and footing construction was in progress. -
ADS21 PC2
¡V Mini-piles construction was in progress. -
DS11 ¡V
Sheetpiling for footing construction was in progress. -
D2-02 ¡V
Watermain laying for fire hydrant was in progress. -
E3-01 ¡V
Backfilling for slope reinstatement was in progress. -
E4
Retaining Wall ¡V Backfilling and road drainage were in progress. -
E4 Ramp
Utrough Bay 17~21 ¡V All profile barriers were completed. -
FW56 Bay
22~25 ¡V All profile barriers were completed. -
Noise
barrier NB109 and NB70 A.
Northbound
¡V Installation of concrete profile barrier at NB109 Bay 1~4 was completed.
Pavement was also reinstated. B.
Southbound
¡V Tentative implementation date of TTA-488 shall be 24 October 2025. -
Noise
barrier NB69 and NB68 A.
NB68 ¡V
Bay 6 stem wall was completed and construction of Bay 5 stem wall was in
progress. Excavation of Bay 1 and 2 was completed and construction of their
footings were in progress. -
Noise
barrier NB 108 A.
Piling
works were commenced on 2 September 2025. 12 out of 48 piles were completed. B.
An
uncharted reinforced concrete was foundation in Bay 4. Design review was in
progress. C.
Sheetpilng
works from Bay 9 to 17 were in progress. -
Noise
barrier NB 66 A.
TTA492
for construction of NB66 was implemented on 17 September 2025. B.
Additional
trial pits to locate abandoned pilecap were carried on 22 September 2025. -
Remaining part of existing
sign gantry FADS8 was removed on 6 August 2025. Noise Barrier NB29 Trough Bay
1-23 A.
Footing
100% completed B.
Wall
(exclude parapet) is 100% completed. Parapet & backfilling & drainage
work in progress. -
Noise barrier NB 30 A.
Drainage
work & backfilling work in progress. -
Noise barrier NB 77 B.
NB77 pile
cap completed, abutment wall construction completed. -
Sign Gantry A.
15 out of
20 columns fabrication were completed. 11 Columns were installed. B.
6 out of
11 mid chords fabrication were completed. FADS11 mid chord was completed. C.
5 out of
11 sign gantries were installed on site. D.
Installation
of DS21B was completed on 10 September 2025. -
Fabrication
of Noise Barrier ¡V 40% of
overall noise barrier columns were completed. Fabrication of NB30 noise
barrier column was in progress. (b)
North
Team -
C1-03,
C4-03 & D1-02 catch pit & manhole construction in progress. -
D1-01,
E2-01, C1-02 & C2-01 watermain works & pillar box for viaduct
completed. D1-04 in progress. -
Backfilling
of B2-03, B2-01, B1-02A & D2-01 in progress. -
JCR:
Construction of new central median & ducting works for traffic signal
& road light were completed of 100%. -
JCR &
Tong Hang Village J/O improvement works (FS 25): slope works 98 % completed. -
JCR &
Tong Hang Village J/O (near bus-stop) : Ducting works for traffic signal
& road light was in progress (100 % completed). -
JCR near
F63 ¡Vslope feature construction works completed. Street furniture in
progress. -
JCR
resurfacing in progress (100% completed) (c)
Bridges
and Structures -
Installation of parapet
and central median for bridge in progress. Parapet construction at bridge E2,
E3, E4, D2 completed. -
Fire hydrant at pier C3-02
completed, installation of fire hydrant at pier E2-01&D2-02 in progress. -
Reinstate of lifting tower
NF83A in progress. Water proofing completed. -
Installation of movement
joint E3-05 completed, total 11 of 20 MJ installation completed. -
Water proofing on bridge
deck in progress, bridge D1, E1, E2, E4, C4R, C3R, C2R, C4L, C3L, C2L
completed. -
Asphalt paving on the deck
in progress, base course of bridge D1, E1, E2, E3, C4R, C3R, C2R, C4L, C3L,
C2L completed. -
Wearing course pavement on
the deck in progress. -
HMFC pavement at C2R and
C3R completed. -
Noise barrier NB28 at
bridge E3 completed. -
Installation of railing on
bridge deck in progress. -
E2 & D2 external
tendon completed, & E3 in progress |
|
ND/2019/06 |
The construction phase was
completed and handed over to AFCD since 4 April 2022. |
|
ND/2019/07 |
(a)
Road works at Portion 3 (b)
C&D waste disposal at Portion 1 and 3 |