Table IV Summary Table for Site Activities in the coming Three
Months
|
Contract No. |
Site Activities (November 2025 to January 2026) |
|
ND/2019/01 |
(a)
Drainage works, watermain
works, site formation and road works in Portion 1a (b)
Site formation, watermain
works, drainage works, sewage works, backfilling, UU works and road works in
Portion 1b and 1c (c)
Site formation,
construction of subway, road works, drainage works, slope works and soil nail
in Portion 2 (d)
HAC soil treatment and watermain
works in Portion 3 (e)
Watermain works, smart
lighting, paving block and road works in Portion 5 (f)
Backfilling, drainage
works, watermain works, slope works, road works and UU works
in Portion 6a and 9c (g)
Storage area in Portion 6b (h)
Excavation, watermains
works, road works, smart lighting, traffic light and paving block in Portion
7 (i)
RC structure works,
drainage works, watermains works, backfilling, planting, metal works, slope
works and E&M works in Portion 8a (j)
Ground treatment,
grouting, watermain works, ELS construction and RC structure works in Portion
8b (k)
Excavation, slope works, road
works, drainage works, watermain works and district cooling system works, and
smart lighting in Portion 9b (l)
Excavation, watermain
works, drainage works, road works, smart lighting and UU works
in Portion 11b (m)
Stockpile of soil in
Portion 13 |
|
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut
and Fill of Slope (e)
Sheet
Piling (f)
Pipe
Jacking (g)
Pipe
laying and bedding (h)
Grouting |
|
ND/2019/03 |
The
construction phase has been completed since 28 March 2025. |
|
ND/2019/04 |
(a)
Back
Filling (b)
Excavation (c)
Grouting (d)
Road
works (e)
E&M
works (f)
Formwork
and Scaffolding Erection (g)
Rebar
Fixing and ELS (h)
Concreting (i)
MIC (j)
Noise
barrier installation |
|
ND/2019/05 |
(a)
Backfilling (b)
Drainage works (c)
Water works (d)
Ducting and Road works (e)
Slope works (f)
Segments erection (g)
ELS (h)
Wall construction |
|
ND/2019/06 |
The construction phase has been completed and
handed over to AFCD since 4 April 2022. |
|
ND/2019/07 |
(a)
Defects
rectification works |