Table IV       Summary Table for Site Activities in the coming Three Months

Contract No.

Site Activities (November 2025 to January 2026)

ND/2019/01

(a)          Drainage works, watermain works, site formation and road works in Portion 1a

(b)         Site formation, watermain works, drainage works, sewage works, backfilling, UU works and road works in Portion 1b and 1c

(c)          Site formation, construction of subway, road works, drainage works, slope works and soil nail in Portion 2

(d)         HAC soil treatment and watermain works in Portion 3

(e)          Watermain works, smart lighting, paving block and road works in Portion 5

(f)          Backfilling, drainage works, watermain works, slope works, road works and UU works in Portion 6a and 9c

(g)         Storage area in Portion 6b

(h)         Excavation, watermains works, road works, smart lighting, traffic light and paving block in Portion 7

(i)           RC structure works, drainage works, watermains works, backfilling, planting, metal works, slope works and E&M works in Portion 8a

(j)           Ground treatment, grouting, watermain works, ELS construction and RC structure works in Portion 8b

(k)         Excavation, slope works, road works, drainage works, watermain works and district cooling system works, and smart lighting in Portion 9b

(l)           Excavation, watermain works, drainage works, road works, smart lighting and UU works in Portion 11b

(m)       Stockpile of soil in Portion 13

ND/2019/02

(a)            Backfilling

(b)           Excavation

(c)            Concreting

(d)           Cut and Fill of Slope

(e)            Sheet Piling

(f)            Pipe Jacking

(g)           Pipe laying and bedding

(h)           Grouting

ND/2019/03

The construction phase has been completed since 28 March 2025.

ND/2019/04

(a)           Back Filling

(b)           Excavation

(c)           Grouting

(d)           Road works

(e)           E&M works

(f)            Formwork and Scaffolding Erection

(g)           Rebar Fixing and ELS

(h)           Concreting

(i)            MIC

(j)            Noise barrier installation

ND/2019/05

(a)        Backfilling

(b)       Drainage works

(c)        Water works

(d)       Ducting and Road works

(e)        Slope works

(f)        Segments erection

(g)       ELS

(h)       Wall construction

ND/2019/06

The construction phase has been completed and handed over to AFCD since 4 April 2022.

ND/2019/07
(Nov 2025 to Dec 2025)

(a)        Defects rectification works