2               PROJECT INFORMATION

Background

2.1         The Kwu Tung North (KTN) and Fanling North (FLN) New Development Areas (NDAs) are one of the important sources of land and housing supply in the medium and long term. The development of the KTN and FLN NDAs will be implemented in phase for full completion by 2031. The Phase 1 of the NDAs development, comprising the Advance Works and First Stage Works, is targeted to be implemented from the second half of 2019 progressively. The Advance and First Stage Works would include site formation, engineering infrastructure works (including roads, drainage, sewerage, waterworks, landscaping works, pumping stations, and fresh water and flushing water service reservoirs), soil remediation, reprovisioning of North District Temporary Wholesale Market, development of a nature park at Long Valley and implementation of environmental mitigation measures.

2.2         The scope of works under the Advance and First Stage Works comprises the following:

a)                   The Advance Works (PWP item No. 7747CL-2) consist of:

i)         site formation of land (including soil remediation) in KTN and FLN NDAs for housing, community facilities and engineering infrastructure;

ii)       construction of roads including the eastern section of Fanling Bypass (FLBP(E)) connecting the FLN NDA to Fanling Highway and other roads with footpaths and cycle tracks, and associated junction/ road improvements;

iii)     engineering infrastructure works including drainage. Sewerage (including two sewage pumping stations), waterworks (including a fresh water service reservoir and a flushing water service reservoir in the KTN NDA), landscape works and slopeworks;

iv)     part expansion and upgrading of Shek Wu Hui Sewage Treatment Works (SWHSTW);

v)        reprovisioning works; and

vi)     implementation of environmental mitigation measures and environmental monitoring and audit (EM&A) programme for the works mentioned in (i) to (v) above.

b)                  The First Stage Works (PWP item No. 7759CL) consist of:

i)         development of a nature park at Long Valley including provision of a visitor centre and a footbridge spanning across Sheung Yue River for connection between these two facilities;

ii)       reprovisioning of two egretry sites in the FLN NDA and enhancement works to an existing egretry site in the KTN NDA;

iii)     site formation of land for a village resite area and a district police station in the KTN NDA;

iv)     engineering infrastructure works including roads, drainage, sewerage, waterbirds, and landscape works; and 

v)        implementation of environmental mitigation measures and environmental monitoring and audit (EM&A) programme for the works mentioned in (i) to (iv) above.


 

2.3         The Project which covers KTN and FLN NDAs is a designated project (DP) under Schedule 3 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499). In October 2013, the EIA Report (AEIAR-175/2013) for the Project was approved by the Director of Environmental Protection pursuant to the EIA Ordinance. The relevant EPs under the Project and the respective Work Contracts are summarised in Tables 2.1a and 2.1.b.

 

Table 2.1a         Summary of EPs under the Project and the Respective Work Contracts

EP No.

Designated Project

C1

C2

C3

C5A

C5B

C6

C7

EP-466/2013/A

Castle Peak Road Diversion

ü

¡@

EP-467/2013/A

Kwu Tung North New Development Area Road P1 and P2 and Associated New Kwu Tung Interchange and Pak Shek Au Interchange Improvement

ü

¡@

EP-468/2013/A

Kwu Tung North New Development Area Road D1 to D5

ü

ü

¡@

EP-469/2013

Sewage Pumping Stations in Kwu Tung North New Development Area

ü

¡@

EP-470/2013/A

Utilization of Treated Sewage Effluent (TSE) from Shek Wu Hui Sewage Treatment Works

ü

¡@

EP-473/2013/A

Fanling Bypass Eastern Section

ü

ü

ü

¡@

EP-475/2013/A

Reprovision of temporary Wholesale Market in Fanling North New Development Area

ü

¡@

EP-546/2017

Fanling North Temporary Sewage Pumping Station

ü

¡@

                Notes: C1: ND/2019/01     C2: ND/2019/02  C3: ND/2019/03  C5A: ND/2019/04

                     C5B: ND/2019/05         C6: ND/2019/06  C7: ND/2019/07

Table 2.1b Summary of Scope of Works under concerned EP

Environmental Permit (EP) No.

Work Contract(s)

Scope of Works under concerned EP(s)

Site Layout Plan under concerned EP(s)

EP-466/2013/A(Part)

C1

Realign Castle Peak Road and join with the Pak Shek Au Interchange at the western end

Figure 12

EP-467/2013/A(Part)

C1

Construction of new primary distributor road (P1) within Kwu Tung North New Development Area

Figure 13

EP-468/2013/A(Part)

C1

Construction of new primary distributor roads (D1, D3, D4 and part of D5) within Kwu Tung North New Development Area

Figure 14

C3

Development of a nature park at Long Valley and ecological mitigation and enhancement works for the nature park (Condition 2.9)

Figure 15

EP-469/2013(Part)

C2

Construction of one sewage pumping station in Kwu Tung North with installed capacity of more than 2,000 m3 per day

Figure 16

EP-470/2013/A(Part)

C1

Construction of service reservoir and watermain for the reuse of treated sewage effluent for reuse in Kwu Tung North Development Areas

Figure 17

EP-473/2013/A(Part)

C3

Establishment of alternative egretry sites and enhance the existing egretry site at Ho Sheung Heung and/or its vicinity (Condition 2.7)

Figure 18

EP-473/2013/A(Part)

C5A

Construction of new district distributor inside FLN NDA, which provides a linkage between the Man Kam To Road and the proposed Fanling Bypass Eastern Section

Figure 19

EP-473/2013/A(Part)

C5B

Figure 20

EP-475/2013/A

C6

The re-provisioned wholesale market will have approximately 1,000 market stalls within a site area of around 1.3 ha

Figure21

EP-546/2017

C5A

Construct and operate a temporary sewage pumping station in Fanling North with installed capacity (average dry weather flow) of about 3,600m3/day

Figure 22

Remark: The EP(s) not related to the Project of the First Phase of the Kwu Tung North (KTN) and Fanling North (FLN) New Development Area (NDA) Development Areas are not included in the Table.

2.4         The site boundary of the Project and all Works Contracts are shown in Drawing No. 1.

2.5         The required submissions and submission status under Environmental Permits are shown in Appendix U.

2.6         The site layout plans under concerned Environmental Permits are shown in Figures 12 - 22.

Project Organization

2.7         Different parties with different levels of involvement in the Project organisation include:

Ÿ    Project Proponent ¡V Civil Engineering and Development Department (CEDD)

Ÿ    Supervisor / Supervisor's Representative ¡V AECOM Asia Co. Ltd.

Ÿ    Environmental Team (ET) ¡V Wellab Limited

Ÿ    Independent Environmental Checker (IEC) ¡V Mott MacDonald Hong Kong Ltd (MottMac)

2.8         The names and contact numbers of key personnel are summarised in Table 2.2.


Table 2.2   Key Contacts of the Project

Party

Role

Contact Person

Phone No.

Fax No.

Civil Engineering and Development Department, HKSAR (CEDD)

Project Proponent

Mr. Ryan Chau

3797 5387

3547 1658

Supervisor / Supervisor's Representative

(AECOM Asia Co. Ltd.)

Chief Resident Engineer

Mr. Alan Lee

6398 5982

2680 9515

Senior Resident Engineer

Mr. King-man Chan

9651 2635

2680 9515

Environmental Team

(Wellab Limited)

Environmental Team Leader

Dr. Priscilla Choy

2898 7388

2898 7076

Independent Environmental Checker (MottMac)

Independent Environmental Checker

Mr. Thomas Chan

2828 5967

2827 1823

Contract No. ND/2019/01

Contractor (Build King ¡V Richwell Engineering Joint Venture)

Site Agent

Mr. Ivan Leung

9640 8340

--

Environmental Officer

Mr. Edward Tam

9287 8270

Contract No. ND/2019/02

Contractor (Chun Wo ¡V Kwan Lee Joint Venture.)

Site Agent

Mr. Andy Chan

3485 9780

--

Environmental Officer

Ms. Barbara Yiu

9758 2034

Contract No. ND/2019/03

Contractor (Sang Hing Kuly Joint Venture)

Site Agent

Mr. Tang Wing Kai

9300 7037

--

Environmental Officer

Mr. Ken Cheung

9803 5297

Contract No. ND/2019/04

Contractor (Daewoo ¡V Chun Wo ¡V Kwan Lee Joint Venture)

Site Agent

Mr. Eric Wu

9786 8630

--

Environmental Officer

Mr. Sam Lam

6178 3179

Contract No. ND/2019/05

Contractor (CRCC ¡V Paul Y. Joint Venture)

Site Agent

Mr. Darvin Lo

9467 5891

--

Environmental Manager

Mr. Pan Fong

9436 9435

Environmental Officer

Ms. Connie Yuen

6316 6931

Contract No. ND/2019/06

Contractor (New Concepts Engineering Development Ltd.)

Project Manager

Mr. Joe Cheng

9861 0060

--

Environmental Officer

Mr. Alex Choy

6360 3236

Contract No. ND/2019/07

Contractor (China Road and Bridge Corporation)

Site Agent

Mr. Mac Chow

9169 9567

--

Environmental Manager

Mr. K. M. Lui

5113 8223

 


 

Summary of Construction Works Undertaken During Reporting Month

2.9         The major site activities undertaken in the reporting month are shown in Table 2.3.

Table 2.3     Summary Table for Major Site Activities in the Reporting Month

Contract No.

Site Activities (October 2025)

ND/2019/01

(a)          Drainage works and watermain works in Portion 1a

(b)         Site formation, watermain works, ELS construction, drainage works, sewage works, backfilling and road works in Portion 1c

(c)          Site formation, construction of subway, drainage works, road works, soil nail and slope works in Portion 2

(d)         HAC soil treatment, watermain works and UU works in Portion 3

(e)          UU works, site formation and watermain works in Portion 5

(f)          Backfilling, drainage works, watermain works, slope works, road works, district cooling system and UU works in Portion 6a and 9c

(g)         Operation of HAC soil treatment facility in Portion 6b

(h)         Excavation, watermain works, sewage works, road works (UU) and smart lighting in Portion 7

(i)           Road works, RC structure works, drainage works, watermains works, backfilling, planting, metal works, slope works and E&M works in Portion 8a

(j)           Ground treatment, grouting, watermain construction, ELS construction and RC structure works in Portion 8b

(k)         Excavation, road works, drainage works, watermain works, district cooling system and smart lighting in Portion 9b

(l)           Drainage works, watermain works and road works in Portion 11b

(m)       Stockpile of soil in Portion 13

ND/2019/02

(a)           Backfilling

(b)           Excavation

(c)            Concreting

(d)           Cut and Fill of Slope

(e)            Sheet Piling

(f)            Pipe Jacking

(g)           Pipe laying and bedding

(h)           Grouting

ND/2019/03

All construction activities with significant environmental impact have been substantially completed in April 2024 and all outstanding works with defect rectification have also been completed on 28 March 2025.

ND/2019/04

(a)           Back Filling

(b)           Excavation

(c)           Grouting

(d)           Road works

(e)           E&M works

(f)            Formwork and Scaffolding Erection

(g)           Rebar Fixing and ELS

(h)           Concreting

(i)            MIC

(j)            Noise barrier installation

ND/2019/05

(a)          South Team

-          BBI Toilet ¡V ABWF and installation bio treatment plant were in progress.

-          BBI Toilet ¡V Dwarf Wall construction was 70% completed.

-          Lift LT01 ¡V Lift installation was completed.

-          Road D400 ¡V Road works for TTA-488 in progress. Tentative implementation date is 24 October 2025.

-          ADS21 PC1 ¡V Excavation completed and footing construction was in progress.

-          ADS21 PC2 ¡V Mini-piles construction was in progress.

-          DS11 ¡V Sheetpiling for footing construction was in progress.

-          D2-02 ¡V Watermain laying for fire hydrant was in progress.

-          E3-01 ¡V Backfilling for slope reinstatement was in progress.

-          E4 Retaining Wall ¡V Backfilling and road drainage were in progress.

-          E4 Ramp Utrough Bay 17~21 ¡V All profile barriers were completed.

-          FW56 Bay 22~25 ¡V All profile barriers were completed.

-          Noise barrier NB109 and NB70

A.         Northbound ¡V Installation of concrete profile barrier at NB109 Bay 1~4 was completed. Pavement was also reinstated.

B.          Southbound ¡V Tentative implementation date of TTA-488 shall be 24 October 2025.

-          Noise barrier NB69 and NB68

A.         NB68 ¡V Bay 6 stem wall was completed and construction of Bay 5 stem wall was in progress. Excavation of Bay 1 and 2 was completed and construction of their footings were in progress.

-          Noise barrier NB 108

A.         Piling works were commenced on 2 September 2025. 12 out of 48 piles were completed.

B.          An uncharted reinforced concrete was foundation in Bay 4. Design review was in progress.

C.          Sheetpilng works from Bay 9 to 17 were in progress.

-          Noise barrier NB 66

A.         TTA492 for construction of NB66 was implemented on 17 September 2025.

B.          Additional trial pits to locate abandoned pilecap were carried on 22 September 2025.

-          Remaining part of existing sign gantry FADS8 was removed on 6 August 2025. Noise Barrier NB29 Trough Bay 1-23

A.         Footing 100% completed

B.          Wall (exclude parapet) is 100% completed. Parapet & backfilling & drainage work in progress.

-          Noise barrier NB 30

A.         Drainage work & backfilling work in progress.

-          Noise barrier NB 77

B.          NB77 pile cap completed, abutment wall construction completed.

-          Sign Gantry

A.         15 out of 20 columns fabrication were completed. 11 Columns were installed.

B.          6 out of 11 mid chords fabrication were completed. FADS11 mid chord was completed.

C.          5 out of 11 sign gantries were installed on site.

D.         Installation of DS21B was completed on 10 September 2025.

-         Fabrication of Noise Barrier ¡V 40% of overall noise barrier columns were completed. Fabrication of NB30 noise barrier column was in progress.

(b)         North Team

-          C1-03, C4-03 & D1-02 catch pit & manhole construction in progress.

-          D1-01, E2-01, C1-02 & C2-01 watermain works & pillar box for viaduct completed. D1-04 in progress.

-          Backfilling of B2-03, B2-01, B1-02A & D2-01 in progress.

-          JCR: Construction of new central median & ducting works for traffic signal & road light were completed of 100%.

-          JCR & Tong Hang Village J/O improvement works (FS 25): slope works 98 % completed.

-          JCR & Tong Hang Village J/O (near bus-stop) : Ducting works for traffic signal & road light was in progress (100 % completed).

-          JCR near F63 ¡Vslope feature construction works completed. Street furniture in progress.

-          JCR resurfacing in progress (100% completed)

(c)          Bridges and Structures

-          Installation of parapet and central median for bridge in progress. Parapet construction at bridge E2, E3, E4, D2 completed.

-          Fire hydrant at pier C3-02 completed, installation of fire hydrant at pier E2-01&D2-02 in progress.

-          Reinstate of lifting tower NF83A in progress. Water proofing completed.

-          Installation of movement joint E3-05 completed, total 11 of 20 MJ installation completed.

-          Water proofing on bridge deck in progress, bridge D1, E1, E2, E4, C4R, C3R, C2R, C4L, C3L, C2L completed.

-          Asphalt paving on the deck in progress, base course of bridge D1, E1, E2, E3, C4R, C3R, C2R, C4L, C3L, C2L completed.

-          Wearing course pavement on the deck in progress.

-          HMFC pavement at C2R and C3R completed.

-          Noise barrier NB28 at bridge E3 completed.

-          Installation of railing on bridge deck in progress.

-          E2 & D2 external tendon completed, & E3 in progress

ND/2019/06

The construction phase was completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)        Road works at Portion 3

(b)        C&D waste disposal at Portion 1 and 3

Construction Programme

2.10     Copies of Contractors¡¦ construction programmes are provided in Appendix A.

Status of Environmental Licences, Notifications and Permits

2.11     A summary of the relevant permits, licences, and/or notifications on environmental protection for this Project is presented in Table 2.4.

Table 2.4       Status of Environmental Licences, Notifications and Permits

Contract No.

Permit / Licence No.

Valid Period

Status

From

To

Environmental Permit (EP)

ND/2019/01

EP-466/2013/A

21/11/2013

N/A

Valid

EP-467/2013/A

27/01/2017

N/A

Valid

EP-468/2013/A

27/01/2017

N/A

Valid

EP-470/2013/A

21/11/2013

N/A

Valid

ND/2019/02

EP-469/2013

21/11/2013

N/A

Valid

ND/2019/03

EP-468/2013/A

27/01/2017

N/A

Valid

EP-473/2013/A

27/01/2017

N/A

Valid

ND/2019/04

EP/473/2013/A

27/01/2017

N/A

Valid

EP/546/2017

16/11/2017

N/A

Valid

ND/2019/05

EP-473/2013/A

27/01/2017

N/A

Valid

ND/2019/06

EP-475/2013/A

13/01/2017

N/A

Valid

Construction Noise Permit (CNP)

ND/2019/01

GW-RN0626-25

16/06/2025

15/10/2025

Renewed to GW-RN1175-25 in the reporting month

GW-RN1013-25

16/09/2025

15/02/2026

Renewed to GW-RN1195-25 in the reporting month

GW-RN0666-25

12/06/2025

11/11/2025

Valid

GW-RN0615-25

19/06/2025

18/11/2025

Valid

GW-RN0860-25

19/08/2025

18/02/2026

Valid

GW-RN0802-25

12/08/2025

11/01/2026

Valid

GW-RN1012-25

06/09/2025

05/02/2026

Valid

GW-RN0992-25

17/09/2025

16/01/2026

Valid

GW-RN1080-25

25/09/2025

24/12/2025

Valid

GW-RN1070-25

25/09/2025

24/01/2026

Valid

GW-RN0865-25

01/09/2025

28/02/2026

Valid

GW-RN0905-25

01/09/2025

28/02/2026

Valid

GW-RN1175-25

16/10/2025

15/01/2026

Valid

GW-RN1195-25

20/10/2025

19/01/2026

Valid

GW-RN1109-25

02/10/2025

01/01/2026

Valid

ND/2019/02

GW-RN0796-25

23/07/2025

22/11/2025

Valid

GW-RN0906-25

21/08/2025

20/12/2025

Valid

GW-RN1007-25

12/09/2025

11/02/2026

Valid

GW-RN1020-25

05/09/2025

04/12/2025

Valid

GW-RN1034-25

15/09/2025

14/01/2026

Valid

ND/2019/04

GW-RN0846-25

04/08/2025

03/12/2025

Valid

GW-RN0963-25

26/08/2025

25/11/2025

Valid

GW-RN1096-25

27/09/2025

26/12/2025

Valid

GW-RN1097-25

27/09/2025

26/12/2025

Valid

GW-RN1098-25

27/09/2025

26/12/2025

Valid

GW-RN1099-25

27/09/2025

26/12/2025

Valid


ND/2019/05

GW-RN0921-25

16/08/2025

31/10/2025

Renewed to GW-RN1027-25 in the reporting month

GW-RN0940-25

19/08/2025

31/10/2025

Expired in the reporting month

GW-RN0989-25

01/09/2025

30/11/2025

Valid

GW-RN0990-25

01/09/2025

28/02/2026

Valid

GW-RN1035-25

01/10/2025

31/12/2025

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

ND/2019/01

451792

11/12/2019

N/A

Valid

477388

02/03/2022

N/A

Valid

ND/2019/02

454012

05/03/2020

N/A

Valid

ND/2019/03

452216

24/12/2019

N/A

Valid

452332

31/12/2019

N/A

Valid

452333

31/12/2019

N/A

Valid

ND/2019/04

461184

23/10/2020

N/A

Valid

ND/2019/05

454323

13/03/2020

N/A

Valid

ND/2019/06

449369

24/09/2019

N/A

Valid

ND/2019/07

459393

28/08/2020

N/A

Valid

Billing Account for Disposal of Construction Waste

ND/2019/01

7036265

17/01/2020

N/A

Valid

ND/2019/02

7036898

01/04/2020

N/A

Valid

ND/2019/03

7036378

22/01/2020

N/A

Valid

ND/2019/04

7038391

22/09/2020

N/A

Valid

ND/2019/05

7036901

01/04/2020

N/A

Valid

ND/2019/06

7035473

17/10/2019

N/A

Valid

ND/2019/07

7038309

14/09/2020

N/A

Valid

Registration of Chemical Waste Producer

ND/2019/01

5213-545-B2578-01

10/01/2020

N/A

Valid

ND/2019/02

5213-548-C4439-01

06/05/2020

N/A

Valid

ND/2019/03

5213-623-S4231-01

14/04/2020

N/A

Valid

ND/2019/04

5211-624-D2709-01

26/11/2020

N/A

Valid

ND/2019/05

5213-625-C4464-01

20/05/2020

N/A

Valid

ND/2019/06

5213-625-N2716-01

02/10/2019

N/A

Valid

ND/2019/07

5213-625-C4498-01

21/09/2020

N/A

Valid

Effluent Discharge License under Water Pollution Control Ordinance

ND/2019/01

WT00037191-2020

21/04/2022

28/02/2026

Valid

WT00037204-2020

16/11/2022

28/02/2026

Valid

WT00037412-2021

05/12/2023

30/04/2026

Valid

WT00037564-2021

19/04/2021

30/04/2026

Valid

WT00037886-2021

28/06/2021

30/06/2026

Valid

WT00041311-2022

21/06/2022

30/06/2027

Valid

WT10001848-2023

05/12/2023

31/12/2028

Valid

WT00044860-2024

29/07/2024

31/07/2029

Valid

WT00044814-2024

08/07/2024

31/07/2029

Valid

WT10002972-2024

07/06/2024

30/06/2029

Valid

WT00046827-2025

30/06/2025

30/06/2030

Valid

WT00046825-2025

30/06/2025

30/06/2030

Valid

WT00046830-2025

30/06/2025

30/06/2030

Valid

WT00046840-2025

30/06/2025

30/06/2030

Valid

ND/2019/02

WT00036584-2020

21/10/2020

31/10/2025

Expired in the reporting month

WT00036952-2020

17/12/2020

31/12/2025

Valid

ND/2019/03

WT00037771-2021

08/07/2021

31/07/2026

Valid

ND/2019/04

WT00037539-2021

02/06/2022

30/04/2026

Valid

ND/2019/05

WT00042471-2022

03/11/2022

30/11/2027

Valid

ND/2019/07

WT00037526-2021

21/04/2022

31/05/2026

Valid