10
ENVIRONMENTAL SITE INSPECTION
10.1 Site audits were carried out by ET on a weekly
basis to monitor the timely implementation of proper environmental management
practices and mitigation measures on the Contract site. Summary of the site audits
are presented in Table 10.1 and Appendix
P.
Table 10.1 Summary
of Site Audits
|
Environmental Site
Inspection |
Works Contracts |
||||||
|
ND/2019/01 |
ND/2019/02 |
ND/2019/03 |
ND/2019/04 |
ND/2019/05 |
ND/2019/06 |
ND/2019/07 |
|
|
Weekly site audit with representative
of the Supervisor¡¦s Representative
and the Contractor |
8, 16, 22 and 28 Oct 25 |
8, 15, 22 and 28 Oct 25 |
N/A |
2, 9, 16, 21 and 30 Oct 25 |
6, 13, 20 and 28 Oct 25 |
N/A |
6, 13, 20 and 28 Oct 25 |
|
Joint Site Audit with representative
of the Supervisor¡¦s Representative,
the Contractor and IEC |
16 Oct 25 |
22
Oct 25 |
N/A |
21 Oct 25 |
20 Oct 25 |
N/A |
20 Oct 25 |
Remarks:
1.
The weekly site inspection for ND/2019/06 has been
terminated starting from 19/10/2023 since the termination proposal was approved
by EPD on the same day.
2.
The weekly site inspection for ND/2019/03 has been
terminated starting from 01/04/2025 since all outstanding works with defect
rectification works was completed on 28 March 2025 according to AECOM.
10.2 During site inspections in the reporting month, no non-conformance was
identified. The observations and recommendations made during the audit sessions
are summarised in Table 10.2. Any outstanding and recurrence deficiencies are
presented in Table 10.3.
10.3 All construction activities with significant environmental impact
undertaken by Contract No. ND/2019/06 was substantially completed in March 2022
and the majority of outstanding works were also completed
in April 2022 with defect rectification works remained until July 2023 when all works were
completed.
10.4 The weekly site inspection and EM&A Reporting for ND/2019/06 were
maintained until the termination proposal for ND/2019/06 has been endorsed by
the IEC (17 Aug 23), the Engineer (26 Aug 23) and the Project Proponent (19 Sep
23) followed by approval from EPD (19 Oct 23) in accordance. The procedure for
termination proposal for ND/2019/06 is in accordance with section 15.4.2 of
updated EM&A Manual.
10.5
Regarding
to Contract No. ND/2019/03, all outstanding works with defect rectification
under the Contract have also been completed on 28 March 2025. Refer to the
proposal for termination of Construction Phase EM&A Programme
of ND/2019/03 submitted by ET, with no objection from CEDD, AECOM and IEC to
EPD in July 2024, weekly site environmental audit under ND/2019/03 was
terminated starting from 1st April 2025. According to the
recommendation from AFCD, Avifauna monitoring in Long Valley (i.e., T5) during
the construction period and its results reporting in the Monthly EM&A
Report will be continued until the completion of works within 200m of Long
Valley.
Table 10.2
Observations and Recommendations during Site Audits
|
Date |
Observations and Recommendations |
Follow-up |
|
|
Contract
No.: ND/2019/01 |
|||
|
-- |
-- |
-- |
-- |
|
Contract
No.: ND/2019/02 |
|||
|
Water Quality |
08/10/2025 |
Drainage system should
be well maintained to avoid surface runoff exceeds site boundary at CH1680. |
Item
was remarked as 251015-R01. Follow-up action is needed to be reviewed. |
|
15/10/2025 |
Improvement/Rectification
was observed during follow-up audit session on 22 October 2025. |
||
|
30/09/2025 |
Used bentonite slurries
should be collected and stored properly. |
Item
was remarked as 251008-R03. Follow-up action is needed to be reviewed. |
|
|
08/10/2025 |
Improvement/Rectification
was observed during follow-up audit session on 15 October 2025. |
||
|
Ecology |
30/09/2025 |
Silt curtain should be
maintained properly and regularly. |
Item
was remarked as 251008-R03. Follow-up action is needed to be reviewed. |
|
08/10/2025 |
Item
was remarked as 251015-R02. Follow-up action is needed to be reviewed. |
||
|
15/10/2025 |
Item
was remarked as 251022-R01. Follow-up action is needed to be reviewed. |
||
|
22/10/2025 |
Item
was remarked as 251028-R01. Follow-up action is needed to be reviewed. |
||
|
28/10/2025 |
Follow-up
action is needed to be reported in the following month. |
||
|
Waste/Chemical Management |
30/09/2025 |
Drip tray for
chemical/fuel containers at CH1680 should be provided. |
Improvement/Rectification
was observed during follow-up audit session on 8 October 2025. |
|
Contract No.: ND/2019/04 |
|||
|
Water Quality |
02/10/2025 |
Sand
bag bunds should be supplemented to avoid surface runoff entering Ng Tung
River. |
Item
was remarked as 251009-R01. Follow-up action is needed to be reviewed. |
|
09/10/2025 |
Improvement/Rectification
was observed during follow-up audit session on 16 October 2025. |
||
|
Waste / Chemical Management |
02/10/2025 |
General
refuse should be disposed of regularly and properly. |
Improvement/Rectification
was observed during follow-up audit session on 9 October 2025. |
|
09/10/2025 |
General
refuse should be disposed of regularly and properly. |
Improvement/Rectification
was observed during follow-up audit session on 16 October 2025. |
|
|
Air Quality |
09/10/2025 |
Stockpile
of dusty material should be covered by impervious sheeting properly or
water-sprayed regularly as dust suppression. |
Item
was remarked as 251016-R01. Follow-up action is needed to be reviewed. |
|
16/10/2025 |
Item
was remarked as 251021-R01. Follow-up action is needed to be reviewed. |
||
|
21/10/2025 |
Item
was remarked as 251030-R01. Follow-up action is needed to be reviewed. |
||
|
30/10/2025 |
Follow-up
action is needed to be reported in the following month. |
||
|
21/10/2025 |
Dust
suppression measures should be enhanced. |
Improvement/Rectification
was observed during follow-up audit session on 30 October 2025. |
|
|
Ecology |
02/10/2025 |
2m high
dull green barrier along the 10m buffer zone should be erected and maintained
properly. |
Improvement/Rectification
was observed during follow-up audit session on 9 October 2025. |
|
16/10/2025 |
2m high
dull green barrier along the 10m buffer zone should be erected and maintained
properly. |
Item
was remarked as 251021-R02. Follow-up action is needed to be reviewed. |
|
|
21/10/2025 |
Improvement/Rectification
was observed during follow-up audit session on 30 October 2025. |
||
|
Contract
No.: ND/2019/05 |
|||
|
Waste/Chemical Management |
20/10/2025 |
Drip tray for chemical/fuel containers should be
provided. |
Improvement/Rectification was
observed during follow-up audit session on 28 October 2025. |
|
Air Quality |
06/10/2025 |
Stockpile of dusty material should be covered by
impervious sheeting properly. |
Improvement/Rectification
was observed during follow-up audit session on 13 October 2025. |
|
20/10/2025 |
NRMM labels on the regulated machines should be
displayed properly. |
Improvement/Rectification
was observed during follow-up audit session on 28 October 2025. |
|
|
Contract No.: ND/2019/07 |
|||
|
-- |
-- |
-- |
-- |
Table 10.3 Summary
Table for the Outstanding item(s) in the
reporting month
|
Contract No. |
Outstanding
deficiencies since last reporting month (September
2025) |
Deficiencies
recorded in
the reporting month (October
2025) |
Total
deficiencies (including repeated deficiencies) in the reporting month |
Deficiencies
rectified in the reporting month |
Outstanding
deficiencies need
to be Follow-up in the next month (November
2025) |
Total outstanding
deficiencies |
||||||||||||||
|
A |
N |
W |
W/C |
CH |
L&V |
E |
P/L |
A |
N |
W |
W/C |
CH |
L&V |
E |
P/L |
|||||
|
ND/2019/01 |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
|
ND/2019/02 |
3 |
/ |
/ |
3 |
/ |
/ |
/ |
4 |
/ |
7 |
3 |
/ |
/ |
/ |
/ |
/ |
/ |
1 |
/ |
1 |
|
ND/2019/03** |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
|
ND/2019/04 |
/ |
5 |
/ |
2 |
2 |
/ |
/ |
3 |
/ |
12 |
6 |
1 |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
1 |
|
ND/2019/05 |
/ |
2 |
/ |
/ |
1 |
/ |
/ |
/ |
/ |
3 |
3 |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
|
ND/2019/06* |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
|
ND/2019/07 |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
Legends:
A = Air Quality
N = Construction Noise Impact
W = Water Quality
W/C = Waste / Chemical Management
CH = Cultural Heritage
L&V = Landscape & Visual
E = Ecology
P/L = Permit / Licences
* The
weekly site inspection for ND/2019/06 has been terminated starting from
19/10/2023 since the termination proposal was approved by EPD on the same day.
** The
weekly site inspection for ND/2019/03 has been terminated starting from
01/04/2025 since all outstanding works with defect rectification works was
completed on 28 March 2025 according to AECOM.
Implementation
Status of Environmental Mitigation Measures
10.6 According to the EIA Report, EPs and the Updated EM&A Manual, the
mitigation measures detailed in the documents are recommended to be implemented
during the construction phase. An updated summary of the Environmental
Mitigation Implementation Schedule is provided in Appendix Q. The photographic records of measures as stipulated in
EPs to mitigate environmental impacts in the reporting month are presented
in Table 10.4.
Table 10.4 Photographic Records and Implementation Status of
Measures
|
EP No. |
Condition |
Photographic
Record |
Implementation
Status |
|
EP-466/2013/A |
2.9 |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m
high solid dull green site barrier fences shall be erected around all active
works areas. |
^[1] |
|
EP-467/2013/A |
2.9 |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m
high solid dull green site barrier fences shall be erected around all active
works areas. |
^[1] |
|
EP-468/2013/A |
2.11 |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the
Project, 2m high solid dull green site barrier fences shall be erected around
all active works areas. |
^[1] |
|
EP-469/2013 |
2.7 |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the
Project, 2m high solid dull green site barrier fences shall be erected around
all active works areas. |
^[1] |
|
EP-473/2013/A |
2.13 |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the
Project, 2m high solid dull green site barrier fences shall be erected around
all active works areas. |
^[1] |
|
EP-475/2013/A |
2.7 |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the
Project, 2m high solid dull green site barrier fences shall be erected around
all active works areas. |
^[1] |
|
Implementation status: |
^ Mitigation
measure was fully implemented * Observation/reminder
was made during site audit but improved/rectified by the contractor # Observation/reminder
was made during site audit but not yet improved/ rectified by the contractor X Non-compliance
of mitigation measure ¡P Non-compliance
but rectified by the contractor N/A Not Applicable at this stage as no such
site activities were conducted in the reporting period |
||
Remark:
[1]: Barrier fences might be
subjected to change according to the phasing plan designed at detailed design
stage
Implementation
Status of Water Quality Mitigation Measures
10.7 The water
quality mitigation measures detailed in the EIA Report and the Updated EM&A
Manual are recommended to be implemented during the construction phase. Water
quality mitigation measures implemented by the contractors were closely
monitored to prevent water pollution, especially during rainy season. An
updated summary of the Environmental Mitigation Implementation Schedule is
provided in Appendix Q. Specific water quality mitigation measures for
major construction works in the reporting month are presented in Table 10.5.
Table 10.5 Specific Water
Quality Mitigation Measures for Major Construction Works in the Reporting Month
|
Works Contracts |
Photographic Records |
|
|
ND/2019/01 |
Hard paved exposed
slope surface |
Provision of
maintenance for the drainage and sump pit around the construction site |
|
ND/2019/02 |
Hard
paved exposed haul road |
Hard
paved exposed slope surface |
|
ND/2019/03 |
Hard paved exposed haul
road |
Watering the main haul
road regularly. |
|
ND/2019/04 |
Concrete
barrier along the site hoarding |
Deployment
of silt curtain around works area in Ng Tung River |
|
ND/2019/05 |
Covering dusty
stockpile at different works area |
Provision of sand bags around works area and sump
pit to prevent the untreated muddy water |
|
ND/2019/07 |
Covering exposed slope surface with tarpaulin |
De-silting
waste water before discharge |
|
Water quality mitigation measures for site(s) in operation phase,
remaining defect works |
||
|
ND/2019/06 |
Hard paved exposed haul
road |
Hard
paved exposed haul road |
Solid
and Liquid Waste Management Status
10.8 Waste generated from Contract Nos. ND/2019/01, ND/2019/02, ND/2019/04, ND/2019/05
and ND/2019/07 included inert
construction and demolition (C&D) materials and non-inert C&D wastes in
the reporting month. The site of ND/2019/06 was handed over to
AFCD for operation since 4 April 2022. The site of ND/2019/03 was handed over to AFCD for operation since 1 April 2025.
10.9 The amount of wastes generated by the
construction works of the Contract Nos. ND/2019/01, ND/2019/02, ND/2019/04, ND/2019/05
and ND/2019/07 during
the reporting month are shown in Appendix
R. The site of ND/2019/06 was
handed over to AFCD for operation since 4 April 2022. The site of ND/2019/03 was handed over to AFCD for operation since 1 April 2025.
10.10 The Contractors are advised to minimise
the wastes generated through recycling or reusing. All mitigation measures
stipulated in the Updated EM&A Manual and waste management plans shall be
fully implemented. The status of implementation of waste management and
reduction measures are summited in Appendix
Q.
Ecological
Mitigation Measures ¡V Creation of Long Valley Nature Park (LVNP)
10.11 Based on the
findings of the EIA Report, the area of Long Valley has been assessed as of high to very
high ecological value and is the largest contiguous area of freshwater wetland
habitats in Hong Kong. To safeguard the ecological value of Long Valley, about
37 hectares of land in Long Valley has been proposed to develop into Long
Valley Nature Park (LVNP) for conserving and enhancing the ecologically
important environment as well as for compensation of the wetland loss due to
the NDA development.
10.12 LVNP is developed according
to the approved Habitat Creation and Management Plan (HCMP) submitted under
EP-468/2013/A. HCMP provides a framework and specifications for development and
management of LVNP and guides the development to maintain and enhance the 37
hectares of low-lying wetland habitats.
10.13 Regarding the design, the zoning of land use in LVNP is intended to
maintain the existing mosaic pattern of wet and dry agriculture, while
controlling the activities that could potentially disturb target habitats and
species. LVNP will be divided into three broad zones of land use as below:
• Biodiversity Zone of about 21 hectares largely designated for
biodiversity conservation through cultivation of specified crops and habitat
management.
• Agricultural Zone of about 11 hectares designated for commercially
focuses crop production and eco-friendly agricultural practice for farming.
• Visitor Zone of about 5 hectares designed to accommodate visitors as
well as storage and other facilities and for educational purposes.
10.14 The construction of LVNP started in late 2019 and has been opened to public starting from 9
November 2024. All
outstanding works with defect rectification under the ND/2019/03
in LVNP have been completed on 28 March
2025. During the construction
period, the progress of construction and wetland enhancement works has been under
observation by different stakeholders including AFCD and green groups. Close
communication between AFCD and CEDD were conducted to exchange views on
conservation, restoration and management of habitats as well as on the planning
and design of the park. In
addition, advices from green groups, Hong Kong Bird
Watching Society (HKBWS) and The Conservancy Association (CA), have been taken on
habitat management of Long Valley and potential effects on habitat and wildlife
of each individual work conducted in Long Valley. The last meeting was held on 18 November
2022 to share the progress of LVNP with different stakeholders, including CEDD,
AFCD, CA, HKBWS, Contractor, ET, IEC and farmers.
10.15 Proposals on wetland creation and restoration, dry agricultural land
creation, pond creation, water treatment wetland and design of irrigation
channel were submitted by the Contractor to achieve the objectives stated in HCMP
and accepted by the Engineer with consent from AFCD before implementation. The
Contractor would consult the stakeholders for recommendations and suggestions on
mitigation measures to minimise the environmental
impacts arising from construction works. The progress of works would be
arranged to minimise impacts to avifauna and maintain
the habitat for avifauna. The photographic records of site activities in LVNP
are presented in Table 10.6.
Table 10.6 Photographic
Records of Site Activities in LVNP
|
Continuing agricultural practice in existing
farmland to maintain habitats in Long Valley |
|
|
Open water Habitat |
Open water Habitat |
|
Creation of wetland with designated habitat for
biodiversity conservation |
|
|
Planting of paddy rice to provide foraging ground
for Yellow-breasted Bunting |
|
|
Enhancement of irrigation
channel to provide reliable water source for farmland in Long Valley |
|
|
Provision of bird island (hidden area) |
Restoring of water flea pond to provide food
source to water birds |
|
Construction of storage sheds for farmers |
Himantopus himantopus |
|
|
|
|
Pied
Avocet, Recurvirostra avosetta |
Wet agricultural land |