Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
|
Contract No. |
Site Activities (September
2025) |
|
ND/2019/01 |
(a)
Drainage
works, watermain works,
sheet piling and slope works
in Portion 1a (b)
Site
formation, watermain works, ELS construction, drainage works, sewage works,
backfilling and road works in Portion 1c (c)
Site
formation, construction of subway, drainage works, road works, soil nail and
slope works in
Portion 2 (d)
HAC soil treatment and watermain works in Portion 3 (e)
UU works,
site formation, watermain works and drainage works in Portion 5 (f)
Backfilling,
drainage works, watermain works, slope works, road works, district cooling
system and UU works in
Portion 6a and 9c (g)
Operation
of HAC soil
treatment facility in Portion 6b (h)
Excavation,
watermain works, sewage works, road works (UU) and drainage works in Portion
7 (i)
Road works, RC structure
works, drainage works, watermains works, backfilling, planting, metal works,
slope works and E&M works in
Portion 8a (j)
Ground treatment,
grouting, watermain construction, ELS construction and RC structure works in Portion 8b (k)
Sheet
piling, excavation, road works, drainage works, watermain works and district
cooling system in Portion 9b (l)
Drainage works and
watermain works in Portion 11b (m)
Stockpile of soil
in Portion 13 |
|
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and Fill of Slope (e)
Sheet Piling (f)
Pipe
Jacking (g)
Pipe laying and bedding (h)
Grouting |
|
ND/2019/03 |
All
construction activities with significant environmental impact have been
substantially completed in
April 2024 and all outstanding works with defect rectification have also been
completed on 28 March 2025. |
|
ND/2019/04 |
(a)
Back Filling (b)
Excavation (c)
Grouting (d)
Road works (e)
Formwork and Scaffolding Erection (f)
Rebar Fixing and ELS (g)
Backfilling (h)
Concreting (i)
MIC (j)
Noise barrier installation |
|
ND/2019/05 |
(a)
South
Team -
BBI
Toilet ¡V ABWF and installation bio treatment plant were in progress. -
BBI
Toilet ¡V Dwarf Wall construction was 70% completed. -
Lift LT01
¡V Lift installation was completed. Testing in progress. -
Road D400
¡V Road works for TTA-488 in progress. Tentative implementation date is 9
October 2025. -
ADS21 PC1
¡V Sheet piling
works completed. Excavation in progress. -
ADS21 PC2
¡V Water main protective measures completed. Mini-piles construction shall
commence on 15 September 2025. -
DS11 ¡V
Sheet piling
for footing construction was in progress. -
D2-02 ¡V
Watermain laying for fire hydrant was in progress. -
E2-03 ¡V
Outfall construction is completed. -
E3-01 ¡V
Temporary working platform is removed. Backfilling for slope reinstatement
was in progress. -
E4
Retaining Wall ¡V Temporary ramp is removed. Backfilling and road drainage
were in progress. -
E4 Ramp
Utrough Bay 17~21 ¡V Profile Barriers were 30% completed. -
FW56 Bay
22~25 ¡V Stem walls and profile barriers were completed. -
Noise
barrier NB109 and NB70 A.
Northbound
¡V Installation of concrete profile barrier at NB109 Bay 1~4 was completed.
Pavement was also reinstated. B.
Southbound
¡V Tentative implementation date of TTA-488 shall be 9 October 2025. -
Noise
barrier NB69 and NB68 A.
NB69 ¡V
Bay 1~2a backfilling was completed. Sheetpiles were extracted. B.
NB68 ¡V
Bay 7 stem wall was completed. Sheetpiles were installed for Bay 1 to 6.
Excavation for Bay 5 to 6 and Bay 1 to 2 were in progress. -
Noise
barrier NB 108 A.
Piling
works were commenced on 2 September 2025. B.
TCSS
ducting and cables were slewed to suit the pile locations. C.
An
uncharted reinforce concrete was foundation in Bay 4. Design review was in
progress. -
Noise
barrier NB 66 A.
Temporary
lighting was installed and central median was removed. B.
Temporary
pavement for shifting Fanling Highway was completed on 10 September 2025. -
Remaining part of existing
sign gantry FADS8 was removed on 6 August 2025. Noise Barrier NB29 Trough Bay
1-23 A.
Footing
100% completed B.
Wall
(exclude parapet) is 90% completed. Parapet section will cast after
backfilling to formation. -
Noise barrier NB 30 A.
Bay 1 to
bay 20 clamp beam completed. B.
Backfilling
work in progress. -
Noise barrier NB 77 C.
NB77 pile
cap completed, wall construction in progress. -
Sign Gantry A.
15 out of
20 columns fabrication were completed. 11 Columns were installed. B.
6 out of
11 mid chords fabrication were completed. FADS11 mid chord was completed. C.
5 out of
11 sign gantries were installed on site. D.
Installation
of DS21B was completed on 10 September 2025. -
Fabrication
of Noise Barrier ¡V 40% of
overall noise barrier columns were completed. Fabrication of NB30 noise
barrier column was in progress. (b)
North
Team -
C1-03,
C4-03 & D1-02 catch pit & manhole construction in progress. -
D1-01,
E2-01, C1-02 & C2-01 watermain works & pillar box for viaduct
completed. D1-04 in progress. -
Backfilling
of B2-03, B2-01, C1-01b & D2-01 in progress. -
JCR:
Construction of new central median & ducting works for traffic signal
& road light were completed of 100%. -
JCR &
Tong Hang Village J/O improvement works (FS 25): slope works 98 % completed. -
JCR &
Tong Hang Village J/O (near bus-stop) : Ducting works for traffic signal
& road light was in progress (100 % completed). -
JCR near
F63 ¡Vslope feature construction works completed. Street furniture in
progress. -
JCR
resurfacing in progress (90% completed) (c)
Bridges
and Structures -
Installation of parapet
and central median for bridge in progress. -
Fire hydrant at pier
C1-02ompleted, installation of fire hydrant at pier E3-02 in progress. -
Reinstate of lifting tower
NF83A in progress. Installation of glasses completed. -
Installation of movement
joint E1-04 & E4-03 completed, total 10 of 20 MJ installation completed. -
Water proofing on bridge
deck in progress, bridge D1, E1, C4R, C3R, C2R, C4L, C3L, C2L completed. -
Asphalt paving on the deck
in progress, base course of bridge D1, E1, C4R, C3R, C2R, C4L, C3L, C2L
completed. -
Wearing course pavement on
the deck in progress. -
HMFC pavement at C2R and
C3R completed. -
Installation of railing
and noise barrier on bridge deck in progress. -
E2 & D2 external
tendon completed, & E3 in progress |
|
ND/2019/06 |
The construction phase was
completed and handed over to AFCD since 4 April 2022. |
|
ND/2019/07 |
(a)
Road works at Portion 3 (b)
C&D waste disposal at Portion 1, 3 and 4 |