Table II  Summary Table for EM&A Activities in the Reporting Month

EM&A Activities

Monitoring Station (s)

Works Contracts

ND/2019/01

ND/2019/02

ND/2019/03

ND/2019/04

ND/2019/05

ND/2019/06

ND/2019/07

1-hr Total Suspended Particulates (TSP) Monitoring

FLN-DMS1

N/A

N/A

N/A

4, 10, 16, 22, 26 and 30 Sep 25

N/A

N/A

N/A

FLN-DMS3

N/A

4, 10, 16, 22, 26 and 30 Sep 25

FLN-DMS5

3, 9, 15, 19, 25 and 29 Sep 25

N/A

KTN-DMS4(B)

3, 9, 15, 19, 25 and 29 Sep 25

N/A

24-hr TSP Monitoring

FLN-DMS1

N/A

N/A

N/A

3, 9, 15, 19, 25 and 29 Sep 25

N/A

N/A

N/A

FLN-DMS3

N/A

3, 9, 15, 19, 25 and 29 Sep 25

FLN-DMS5A

3, 9, 15, 19, 25 and 29 Sep 25

N/A

KTN-DMS4(B)

3, 9, 15, 19, 25 and 29 Sep 25

N/A

Noise Monitoring

CP-FLN-NMS1

N/A

4, 10, 16, 22 and 30 Sep 25

N/A

N/A

CP-FLN-NMS2

N/A

4, 10, 16, 22 and 30 Sep 25

N/A

CP-KTN-NMS2

3, 9, 15, 25 and 29 Sep 25

N/A

N/A

CP-KTN-NMS3

CP-KTN-NMS5

CP-KTN-NMS6

N/A

3, 9, 15, 25 and 29 Sep 25

Ecological Survey

Monitoring of Measures to Minimise Disturbance to Water Birds on Ng Tung River, Sheung Yue River, and Long Valley

N/A

5, 12, 18 and 26 Sep 25

N/A**

4, 9, 19 and 25 Sep 25

N/A

N/A

N/A

Monitoring of Measures to Minimise Impacts to Ma Tso Lung Stream and Siu Hang San Tsuen Stream

30 Sep 25

N/A*

N/A

30 Sep 25

N/A*

N/A*

N/A*

Monitoring of Measures to Minimise Impacts on Ecological Sensitive Habitats from Disturbance and Pollution

18 and 25 Sep 25

18 and 25 Sep 25

N/A

25 Sep 25

25 Sep 25

N/A*

N/A*

Egretry Monitoring

N/A

N/A

N/A

N/A

N/A

N/A

N/A

24-hr RSP (Ambient Arsenic) Monitoring for Land Contamination

3, 9, 15, 19, 25 and 29 Sep 25

N/A

N/A

N/A

N/A

N/A

N/A

Water Quality Monitoring

N/A

1, 3, 5, 8, 10, 12, 15, 17, 19, 22, 25, 27 and 29 Sep 25

N/A

1, 3, 5, 8, 10, 12, 15, 17, 19, 22, 25, 27 and 29 Sep 25

N/A

N/A

N/A

Landfill Gas Monitoring

11 Sep 25

N/A

N/A

N/A

N/A

N/A

N/A

Built Heritage Monitoring

N/A

N/A

N/A

N/A

N/A

N/A

N/A

Environmental Site Inspection

2, 9, 17, 23 and 29 Sep 25

3, 10, 17, 23 and 30 Sep 25

NIL

4, 11, 18 and 25 Sep 25

1, 9, 16, 22 and 29 Sep 25

NIL

4, 9, 15, 22 and 29 Sep 25

 



 

 

Remarks:  

N/A – No relevant monitoring is required according to the updated EM&A Manual

N/A* – No relevant monitoring is required according to the Baseline Ecological Monitoring Plan (Table 3.1)

[1] Since the distance between monitoring station CP-KTN-NMS2 and site boundary of ND/2019/03 under EP-468/2013/A exceeds 300m, the monitoring station is not applicable to ND/2019/03

[2] Since the distance between monitoring station CP-KTN-NMS3 and site boundary of ND/2019/03 under EP-468/2013/A exceeds 300m, the monitoring station is not applicable to ND/2019/03

[3] Since the distance between monitoring station CP-KTN-NMS1 and site boundary of ND/2019/02 under EP-469/2013 exceeds 300m, the monitoring station is not applicable to ND/2019/02

[4] Since the distance between monitoring station FLN-DMS1 and site boundary of ND/2019/05 under EP-473/2013/A exceeds500m, the monitoring station is not applicable to ND/2019/05

[5] Since the distance between monitoring station FLN-DMS3 and site boundary of ND/2019/03 and ND/2019/04 under EP-473/2013/A exceeds 500m, the monitoring station is not applicable to ND/2019/03 and ND/2019/04

[6] Since the distance between monitoring station FLN-DMS5 and site boundary of ND/2019/05 under EP-473/2013/A exceeds 500m, the monitoring station is not applicable to ND/2019/05

[7] Since the distance between monitoring station CP-FLN-NMS2 and site boundary of ND/2019/03 and ND/2019/04 under EP-473/2013/A exceeds 300m, the monitoring station is not applicable to ND/2019/03 and ND/2019/04

[8] Since the distance between monitoring station CP-FLN-NMS1 and site boundary of ND/2019/03 under EP-473/2013/A exceeds 300m, the monitoring station is not applicable to ND/2019/03

N/A** – According to the recommendation from AFCD, Avifauna monitoring in Long Valley (i.e., T5) during the construction period and its results reporting in the Monthly EM&A Report will be continued until the completion of works within 200m of Long Valley.