Table 11.1    Summary Table for Site Activities in the coming Two Months

 

Contract No.

Site Activities (August and September 2020)

ND/2019/01

 

(a)       Ground Investigation in Portion 1f;

(b)       Site Clearance, Ground Investigation in Portion 2

(c)       Tree Survey, Site Clearance in Portion 3

(d)      Sampling and testing for site trial for In-situ cement mixing (ICM) for soil treatment works in Portion 4

(e)       Site Clearance, Ground Investigation in Portion 5

(f)        Site Clearance, Ground Investigation in Portion 6a;

(g)       Completion of Soil Treatment Facility, Pilot trial for Ex-situ cement mixing (ECM) for soil treatment, provide soil treatment for HAC soil by ECM in Portion 6b;

(h)       Site Clearance, Tree felling, Construction of temporary road for alternative Po Lau Road, Land contamination assessment in Area T1, T2 & T3 in Portion 7;

(i)        Ground Investigation, Construction of Retaining Wall in Portion 8a;

(j)        Site Clearance, Ground Investigation, stockpile of soil in Portion 9c;

(k)       Site Clearance, Tree felling, Excavation in Portion 10a; and

(l)        Site Clearance in 10b

ND/2019/03

 

(a)         Road and Drainage work in Portion 1;

(b)         Initial Restoration Work at Long Valley, Construction works of storage shed and Type 2 Storage House, construction of metal wire railing, site clearance in Portion 2 to 20;

(c)         Pre-relocation survey in Portion 23 and 24

ND/2019/06

 

(a)         Construction of Management Office Building;

(b)        Installation of entrance gate at new run-in/out

(c)         Breaking up the concrete surface and disposal of C&D material off site at Portion 3

(d)        Construction of footings of steel canopy of final stage market

(e)         Ground investigation works at Portion 3

(f)         Tree felling at Portion 3 and 6.