Table 6.1    Summary Table for Site Activities in the coming Two Months

Contract No.

Contract Title

Site Activities (April and May 2020)

Contract No. ND/2019/01

 

Kwu Tung North New Development Area, Phase 1: Site Formation and Infrastructure Works

(a)     Tree Survey, Site Clearance, Ground Investigation, Preparation Works and construction for Interim CLC in Portion 1f;

(b)     Tree Survey, Application of Excavation Permit (XP), Preparation of TTA Drawings for Approval, Ground Investigation in Portion 2;

(c)     Tree Survey, Site Clearance in Portion 3;

(d)    Tree Survey, Site Clearance in Portion 4;

(e)     Site Clearance, GI Works in Portion 5;

(f)      Tree Survey, Site Clearance, Demolish Abandoned Structures of Community Sports, Ground Investigation in Portion 6a;

(g)     Tree Survey, Site Clearance, Ground Investigation, Set up of Soil Treatment Plant in Portion 6b;

(h)     Tree Survey, Site Clearance, Ground Investigation in Portion 7;

(i)      Tree Survey, Site Clearance, Forming Access, GI Works and General Excavation in Portion 8a;

(j)      Tree Survey, Site Clearance in Portion 8b; and

(k)     Container Office in additional land next to Portion 1f.

 

Contract No. ND/2019/06

 

Fanling North New Development Area, Phase 1: Re-provisioning of North District Temporary Wholesale Market for Agricultural Products

(a)       Breaking up the remaining concrete surface and disposal of C&D material off site at Portion 1;

(b)       Installation of road kerbs for interim stage;

(c)       Drainage works for interim stage including construction of U-channel and manhole for interim stage;

(d)      Construction of road surface for interim stage; and

(e)       Construction of footing of lighting for interim stage; and

(f)        Construction of run-in/out.