Contract No. ND/2019/01
Kwu Tung North New Development Area, Phase 1:
Site Formation and Infrastructure Works
Scope
:
The works mainly comprise site formation of land under the First Phase of KTN NDA (including soil treatment works); construction of engineering infrastructures including drainage works, sewerage works (including temporary sewage treatment facilities), waterworks (including a fresh water service reservoir and a flushing water service reservoir), roadworks (including carriageway, footpaths, cycle tracks, a subway and junction improvement), pipeworks for district cooling system, slope works and landscaping works; and construction of associated environmental mitigation works including noise barriers/noise enclosures and low noise road surfacing.
Commencement Date
:
06 December 2019
Completion Date
:
early 2026
Contract Sum
:
$2.578 Billion
Contractor
:
Build King - Richwell Engineering Joint Venture
Contract No. ND/2019/02
Kwu Tung North New Development Area, Phase 1:
Roads and Drains between Kwu Tung North New Development Area and Shek Wu Hui
Scope
:
The contract mainly comprises road and drainage works between Kwu Tung North New Development Area and Shek Wu Hui; construction of a sewage pumping station, a visitor centre for Long Valley Nature Park and a footbridge spanning across Sheung Yue River; and site formation of land and the associated engineering infrastructure works for a village resite area in Kwu Tung North New Development Area.
Commencement Date
:
17 February 2020
Completion Date
:
end 2024
Contract Sum
:
$598 million
Contractor
:
Chun Wo - Kwan Lee Joint Venture
Contract No. ND/2019/03
Kwu Tung North and Fanling North New Development Area, Phase 1:
Development of Long Valley Nature Park
Scope
:
The contract mainly comprises development of a nature park at Long Valley and ecological mitigation and enhancement works for the nature park.
Commencement Date
:
19 December 2019
Completion Date
:
end 2022
Contract Sum
:
$324 million
Contractor
:
Sang Hing – Kuly Joint Venture
Contract No. ND/2019/04
Fanling North New Development Area, Phase 1:
Fanling Bypass Eastern Section (Shek Wu San Tsuen North to Lung Yeuk Tau)
Scope
:
The contract mainly comprises construction of an approximately 2-kilometre-long dual two-lane Fanling Bypass Eastern Section between Shek Wu San Tsuen North and Lung Yeuk Tau comprising viaduct, at-grade road and underpass sections; construction of Lung Yeuk Tau Interchange connecting Fanling Bypass Eastern Section with existing Sha Tau Kok Road – Lung Yeuk Tau; construction of a footbridge across Ng Tung River and a cycle track cum footbridge over Lung Yeuk Tau Interchange; construction of a sewage pumping station adjacent to Lung Yeuk Tau Interchange; reprovisioning of the On Lok Mun Street Playground, public toilet and refuse collection point near Lung Yeuk Tau Interchange; road junction improvement works in the North District; and associated ground investigation, geotechnical instrumentation and monitoring, slope and retaining wall works, drainage and sewerage works, waterworks, noise barrier works, traffic control and surveillance system installation, electrical and mechanical works and landscaping works.
Commencement Date
:
14 August 2020
Completion Date
:
mid 2025
Contract Sum
:
$2.148 Billion
Contractor
:
DCK JV
Contract No. ND/2019/05
Fanling North New Development Area, Phase 1:
Fanling Bypass Eastern Section (Shung Him Tong to Kau Lung Hang)
Scope
:
The contract mainly comprises construction of an approximately 2 kilometres (km) long dual two-lane Fanling Bypass Eastern Section between Shung Him Tong and Kau Lung Hang mainly on viaducts with two long span overbridges across the existing East Rail Line; realignment of part of the existing Tai Wo Service Road East, Tai Wo Service Road West and Fanling Highway; construction of approximately 2.4 km long noise barriers, and relocation of approximately 400 metres long existing noise barriers along Fanling Highway; alteration and addition works to the existing Ho Ka Yuen footbridge; reprovisioning of a bus-bus interchange at Fanling Highway with a proposed public toilet and covered walkway; and associated slope works, ground investigation, geotechnical instrumentation and monitoring, retaining wall, drainage works, waterworks, sewerage works, traffic control and surveillance system installation, electrical and mechanical works and landscaping works.
Commencement Date
:
02 March 2020
Completion Date
:
early 2025
Contract Sum
:
$2.268 Billion
Contractor
:
CRCC – Paul Y. Joint Venture
Contract No. ND/2019/06
Fanling North New Development Area, Phase 1: Reprovisioning of
North District Temporary Wholesale Market for Agricultural Products
Scope
:
The contract mainly comprises construction of an in-situ reprovisioned NDTWM and its facilities involving a steel canopy for the trading area and a management office building.
Commencement Date
:
27 September 2019
Completion Date
:
17 March 2022 (Actual Completion)
Contract Sum
:
$229 million
Contractor
:
New Concepts Engineering Development Limited
Contract No. ND/2019/07
Fanling North New Development Area, Phase 1:
Site Formation and Infrastructure Works
Scope
:
The works mainly comprise site formation of land under the First Phase of Fanling North New Development Area; and construction of engineering infrastructures including drainage and sewerage works, waterworks, roadworks (including carriageway, footpaths and cycle tracks), noise barrier works, slope works and landscaping works.